Agreement No. CE 20/2004(EP) North East New Territories (NENT) Landfill Extension

 

Quarterly Environmental Monitoring and Audit Report (No. 3) – July to September 2023

2023-10-13

ET Certification

IEC Verification

Contents

Executive Summary  1

1.  Introduction. 3

2.  Project Information. 5

3.  Air Quality Monitoring. 8

4   Noise Monitoring. 13

5   Water Quality Monitoring. 17

6   Waste Management 25

7   Landfill Gas Monitoring. 26

8   Landscape and Visual 29

9   Cultural Heritage. 30

10 Ecological Monitoring. 31

11 Site Inspection and Audit 33

12 Environmental Non-conformance. 40

13 Implementation Status on Environmental Mitigation Measures. 43

14 Conclusion. 44

 

Figure

Figure 1

Location of the Project Site

Figure 2

Impact Monitoring Locations

Figure 3

Landfill Gas Monitoring Locations

Appendix

Appendix A

Construction Programme

Appendix B

Construction Site Activities

Appendix C

Project Organization Chart & Management Structure

Appendix D

Detail Status of FEP & EP Submission

Appendix E

Graphical Presentations

Appendix F

Notification of Environmental Quality Limits Exceedance

Appendix G

Waste Flow Table

Appendix H

Environmental Mitigation Implementation Schedule (EMIS)

Appendix I

Mitigation Measures of Cultural Landscape Features

Appendix J

Cumulative complaint / enquiry log, Summaries of complaints and enquiries & Environmental complaint reports

 


Executive Summary

Aurecon Hong Kong Limited (Aurecon) was appointed to undertake the role of Environmental Team (ET) and carry out Environmental Monitoring and Audit for the North East New Territories (NENT) Landfill Extension.

 

The construction phase and EM&A programme of the Project commenced on 1 December 2022.

 

This 3rd Quarterly EM&A Report presents the EM&A works conducted from 1 July to 30 September 2023 in accordance with the EM&A Manual.

Summary of Construction Works undertaken during Report Period

The major construction works undertaken during the reporting period include:

Construction Activities Undertaken

Reporting Month

Jul 2023

Aug 2023

Sep 2023

-  Material loading and unloading, site traffic

-  Permanent site office foundation works with pouring of concrete

 

-  Construction of site buildings

 

 

-  Site clearance

-  Installation of permanent fencing

-  Site formation

-  Tree felling

Shotcreting (Permanent and Temporary)

 

 

 

Environmental Exceedance

 

Air Quality, Noise & Landfill Gas Monitoring

No exceedance of the Action and Limit Levels were recorded at designated monitoring stations during the reporting period.

 

Surface Water Quality Monitoring

No exceedance of the Action and Levels was recorded at designated monitoring stations in July 2023. One DO exceedance of the Action Level was recorded at Surface Water Quality Monitoring (WQM) Location WM1 in August 2023. No exceedance of the Limit Level was recorded at Surface WQM Location WM1 in August 2023. No exceedance of the Action and Limit Levels were recorded at Surface WQM Location WM2 in August 2023. No exceedance of the Action and Levels was recorded at designated monitoring stations in September 2023.


 

Environmental Non-conformance/Compliant/Summons and Prosecution

 

One warning regarding suspected non-compliance event with Condition 1.7 and 2.15(a) of the EP & Condition 1.7 and 2.13(a) of the FEP-01 & FEP-02 was recorded during the reporting period. The related rectified actions are being taken in progress by the contractor.

 

No summons/prosecutions were recorded and received in this reporting period.

 

Three Complaint received on 3 and 18 August 2023 & 14 September 2023 were recorded during the reporting period. For the complaint received on 3 August 2023, the further mitigation measures and enhancement of the temporary surface water drainage system were advised to implement by contractor. For the complaint received on 18 August & 14 September 2023, The related rectified actions should be conducted by the contractor as soon as possible.

1.                  Introduction

1.1.              Background

1.1.1.            The North East New Territories Landfill Extension (the NENTX Project) is located adjacent to the existing North East New Territories (NENT) Landfill at Ta Kwu Ling. The extension site is located in a valley covering mainly the existing NENT Landfill Stockpile and Borrow Area that was formed to the east of the existing landfill as part of the original site development of the landfill, and layout plan shown in Figure 1.

1.1.2.            The NENTX is a designated project. The Environmental Impact Assessment (EIA) Report (AEIAR-111/2007) and an Environmental Monitoring and Audit Manual were approved on 20 September 2007. The project is governed by an Environmental Permit (EP) (EP-292/2007) which was granted on 26 November 2007. A further of EP (FEP) was applied and the FEP (FEP-01/292/2007) was subsequently granted on 28 April 2022. Another further of EP (FEP-02/292/2007) was subsequently granted on 23 August 2023.

1.1.3.            In accordance with the requirements specified in Section 2.6 to 2.10 and Section 12.3 of the approved Environmental Monitoring and Audit (EM&A) Manual, Quarterly EM&A report should be submitted to the Director of Environmental Protection (DEP) within 10 working days after the end of the reporting quarter. The submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC).

1.1.4.            The construction phase and EM&A programme of the Project commenced on 1 December 2022.

1.2.              Nature, Scale and Scope of the captioned Designated Project

1.2.1           The Nature, Scale and Scope of the captioned Designated Project is presented in Table 1-1.

Table 1-1     Nature, Scale and Scope of the captioned Designated Project

Item(s)

Content

Nature of Designated Project

Construction and operation of a landfill for waste as defined in the “Waste Disposal Ordinance” (Cap. 354)

Scale and Scope of Designated Project

The Project mainly consists of the followings: -

Construction and operation of a landfill extension of about 70 hectares with a target void space of at least 19 million cubic metres on the eastern side of the existing NENT Landfill, including the followings: -

   i.           Site formation and preparation;

 ii.          Installation of liner system;

iii.          Installation of leachate collection, treatment and disposal facilities;

iv.           Installation of gas collection, utilization and management facilities;

 v.           Utilities provisions and drainage diversion;

vi.           Landfilling operation;

vii.          Restoration and aftercare in subsequent stages; and

viii.       Measures to mitigate environmental impacts as well as environmental monitoring and auditing to be implemented.


 

1.3.              Purpose of this Report

1.3.1.            This is the 3rd Quarterly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from 01 July to 30 September 2023.

1.4.              Structure of the Report

1.4.1.            The structure of the report is as follows:

Section 1 – Introduction

-       details the background, purpose and structure of the report.

Section 2Project Information

-       summarises background and scope of the Project, site description, project organization and contact details, construction programme, the construction works undertaken and the status of Environmental Permit(s)/License(s) during the reporting period.

Section 3 – Air Quality Monitoring

-       Construction Dust

Section 4 – Noise Monitoring

Section 5 – Water Quality Monitoring

-       Groundwater Monitoring

-       Surface Water Monitoring

Section 6 – Waste Management

Section 7 – Landfill Gas Monitoring

Section 8 – Landscape and Visual

Section 9 – Cultural Heritage

Section 10 – Ecological Monitoring

Section 11 – Site Inspection and Audit

Section 12 – Environmental Non-Conformance

Section 13 – Implementation Status on Environmental Mitigation Measures

Section 14 – Conclusion


2.                  Project Information

2.1.              Construction Activities

2.1.1.            A summary of the major construction activities undertaken in this reporting period is shown in Table 2-1. Construction programme is illustrated in Appendix A. Detailed construction activities are summarized in Appendix B.

Table 2-1       Major Construction Activities Undertaken in the Reporting Period

Construction Activities Undertaken

Reporting Month

Jul 2023

Aug 2023

Sep 2023

-  Material loading and unloading, site traffic

-  Permanent site office foundation works with pouring of concrete

 

-  Construction of site buildings

 

 

-  Site clearance

-  Installation of permanent fencing

-  Site formation

-  Tree felling

Shotcreting (Permanent and Temporary)

 

 

2.2.              Project Organization & Management Structure

2.2.1.            The Project Organization Chart & Management Structure are shown in Appendix C. The key personnel contact information is summarized in Table 2-2.

Table 2-2       Contact Information of Key Personnel

Party

Name

Contact Number

Contractor

(Veolia Hong Kong Holding Ltd.)

Mr. Matt Choy

2902 5296

Independent Environmental Checker (IEC)

(Meinhardt Infrastructure and Environment Ltd.)

Ms. Claudine Lee

2859 5409

Environmental Team Leader (ETL)

(Aurecon Hong Kong Limited)

Mr. Fredrick Leong

3664 6888


 

2.3.              Status of Submission required under the FEP & EP during reporting period

2.3.1.            The status of statutory environmental compliance with the EP conditions under the EIAO, submission status under the FEP & EP during reporting period are presented in Table 2-3. The detail status of statutory environmental compliance with the EP conditions under the EIAO, submission status under the FEP & EP for NENTX project are shown in Appendix D.

Table 2-3        Status of Submissions required under the FEP & EP during reporting period

FEP Condition

EP Condition

Submission / Measures

Status

2.1

2.3

Management Organization of Main Construction Companies

Submitted

2.2

2.4

Setting up of Community Liaison Group

Community Liaison Group was set up.

2.3

2.5

Submission of EM&A Manual

Submitted

2.5

2.7

Submission of Vegetation Survey (Transplantation Proposal)

Submitted

2.6

2.8

Submission of translocation proposal

Submitted

2.7

2.9

Submission of Transplantation Report and Post-Transplantation Monitoring

Submitted

12th monitoring (18 Jul 2023)

13th monitoring (11 Aug 2023)

14th monitoring (15 Sep 2023)

2.8

2.10

Submission of Translocation Report and Post-Translocation Monitoring

Translocation was carried out and the report submitted.

12th monitoring (12 Jul 2023)

2.9

2.11

Submission of Detailed Landfill Gas Hazard Assessment Report

Submitted

2.10

2.12

Submission of Waste Management Plan

Submitted

3.2

3.2

Submission of Baseline Monitoring Report

Submitted

3.3

3.3

Submission of Monthly EM&A Report

8th report (Jul 2023)

9th report (Aug 2023)

10th report (Sep 2023)



2.4.              Status of Environmental Approval Document

2.4.1.            A summary of the relevant valid permits, licences, and/or notifications on environmental protection for this Project since the granting of the EP is presented in Table 2-4.

Table 2-4  Summary of the relevant valid permits, licences, and/or notifications on environmental protection

Permit / Licenses / Notification

Reference

Expiry Date

Remark

Environmental Permit (EP)

EP-292/2007

Throughout the Contract

Permit granted on 26

November 2007

Further Environmental Permit (FEP)

FEP-01/292/2007

Throughout the Contract

Permit granted on 28

April 2022

Further Environmental Permit (FEP)

FEP-02/292/2007

Throughout the Contract

Permit granted on23 August 2023

Notification of Construction Works as required under Air Pollution Control (Construction Dust) Regulation

 479809

Throughout the Construction Phase

Notified on 13 May 2022

Registration of Waste Producer under Waste Disposal Ordinance

7043692

Throughout the Contract

Registered on 13 April 2022

Registration as Chemical Waste Producer

 

5213-642-P1034-18

Throughout the Contract

Registered on 11 July 2022

Construction Noise

Permit

GW-RN0619-23

22 September 2023

Permit granted on 16 June 2023

Construction Noise

Permit

GW-RN1012-23

22 December 2023

Permit granted on 22 September 2023 (Replaced CNP No. GW-RN0619-23)

Effluent Discharge License under Water Pollution Control Ordinance

WT00042301-2022

31 October 2027

Permit granted on 18 October 2022

Variation of Licence (Permit granted on 7 February 2023)


 

3.              Air Quality Monitoring

3.1                  Construction Dust

3.1.1       Monitoring Requirement

3.1.1.1      In accordance with the EM&A Manual, 1-hr & 24-hr Total Suspended Particulates (TSP) levels should be measured at the designated air quality monitoring stations in every 6 days to ensure that any deteriorating air quality could be readily detected, and timely action shall be undertaken to rectify such situation. For 1-hr TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs. The specific time to start and stop the 24- hr TSP monitoring shall be clearly defined for each location.

3.1.2       Monitoring Parameters, Frequency and Location

3.1.2.1      According to the EM&A Manual, three monitoring stations namely AM(D)1, AM(D)2 and AM(D)3 are selected for the impact monitoring.

 

3.1.2.2      A baseline monitoring plan has been submitted to IEC and EPD on 31 May 2022 including the proposal with justification of change of monitoring locations. Due to limited access to the original monitoring locations at AM(D)1, AM(D)2 and AM(D)3, the adjusted stations at AM1, AM2 and AM3 were agreed with IEC prior to the baseline and impact monitoring. The locations of adjusted dust monitoring locations are shown in Figure 2.

 

3.1.2.3      The locations of dust monitoring stations are shown in Table 3-1. The monitoring parameters, frequency and duration are shown in Table 3-2.

Table 3-1          Locations of Dust Monitoring Stations

Monitoring Station

Representative

for

Monitoring Parameters

AM1

Tung Lo Hang

1-hr and 24-hr TSP

AM2

Heung Yuen Wai

1-hr and 24-hr TSP

AM3

Wo Keng Shan Tsuen

1-hr and 24-hr TSP

Remarks:

The contractor passed correspondence including original monitoring locations specified on the Approved EM&A Manual to the village representatives on 26 April 2022. After a meeting with Ta Kwu Ling District Rural Committee (RC) Chairman, representative from the RC and a few villagers on 1 May 2022, all the Village Heads of Wo Keng Shan Tsuen, Heung Yuen Wai and Lin Ma Hang verbally refused to accept our proposal for installation of dust and / or noise monitoring equipment within or next to their villages, for the baseline & impact monitoring.

AM(D)1 Tung Lo Hang, AM(D)2 Heung Yuen Wai, AM(D)3 Wo Keng Shan Tsuen are the air monitoring stations for the construction phase EM&A programme as identified in the approved EM&A Manual for the Project. The access to Tung Lo Hang, Heung Yuen Wai and Wo Keng Shan Tsuen were denied.  A search for alternative air monitoring locations (AM1, AM2 & AM3) was carried out during the site visit.

The Baseline Monitoring Plan has been submitted to IEC and EPD including the proposal of change of monitoring locations on 31 May 2022. This arrangement was conducted between baseline and impact monitoring and has been agreed by the Independent Environmental Checker (IEC) and no comment received from EPD.

Due to the adjustment of the location of AM(D)1, AM(D)2 & AM(D)3to AM1, AM2 & AM3, the measured air quality levels at AM1, AM2 & AM3 would represent the air quality levels at AM(D)1, AM(D)2 & AM(D)3.


 

Table 3-2          Dust Impact Monitoring Parameters, Frequency and Duration

Monitoring Station

Parameter

Frequency and Duration

AM1, AM2, AM3

1-hr TSP

At least 3 times per 6 days

24-hr TSP

1 time per 6 days

3.1.3       Monitoring Results

3.1.3.1      The impact dust monitoring results are summarized in Table 3-3 and Table 3-4. The graphical presentations of monitoring data are presented in Appendix E.

Table 3-3          Summary of Impact 1-hr TSP Monitoring Results

Dust Monitoring Station

Average 1-hr TSP Concentration, µg/m³ (Range)

Action Level, µg/m³

Limit Level, µg/m³

Jul 2023

Aug 2023

Sep 2023

AM1

35

(21 – 46)

33

(20 – 40

44

(36 – 54)

>285

>500

 AM2

34

(21 – 48)

35

(29 – 40)

39

(36 – 42)

>279

>500

AM3

32

(21 – 44)

39

(29 – 50)

45

(36 – 53)

>285

>500

Table 3-4          Summary of Impact 24-hr TSP Monitoring Results

Dust Monitoring Station

Average 24-hr TSP Concentration, µg/m³ (Range)

Action Level, µg/m³

Limit Level, µg/m³

Jul 2023

Aug 2023

Sep 2023

AM1

36

(17 – 60)

29

(19 – 37)

40

(32 – 48)

>164

>260

 AM2

34

(25 – 48)

33

(27 – 43)

41

(30 – 53)

>152

>260

AM3

30

(22 – 40)

40

(2763)

51

(36 – 67)

>163

>260

 

3.1.3.2      The Summary of Impact 1-hr & 24-hr TSP Exceedance are shown in Table 3-5.


 

Table 3-5          Summary of Impact 1-hr & 24-hr TSP Exceedance

Dust Monitoring Station

Parameter

1-hr TSP

Exceedance Count

Accumulate of project

24-hr TSP

Exceedance Count

Accumulate of project

Level Exceedance

AM1

Action

0

0

0

0

0

2*

Limit

0

0

0

0

0

3*

 AM2

Action

0

0

0

0

0

0

Limit

0

0

0

0

0

0

AM3

Action

0

0

0

0

0

4*

Limit

0

0

0

0

0

3*

Remarks: * equal to non-project related

3.1.3.3      No Action / Limit Level exceedance for 1-hr & 24-hr TSP impact monitoring at AM1, AM2 & AM3 was recorded during the reporting period. The Notification of Environmental Quality Limits Exceedances are presented in Appendix F.

3.1.4       Recommended Mitigation Measures

3.1.4.1      The recommended dust mitigation measures from EIA report are listed as followed:

 

           The contractor shall follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation.

           Dust emission from construction vehicle movement is confined within the worksites area.

           Watering facilities will be provided at every designated vehicular exit point.

           Good site practice is recommended during construction phase.

3.1.5       Event and Action Plan

3.1.5.1      Should non-compliance of the criteria occur, action in accordance with the action plan in Table 3-6 shall be carried out.

Table 3-6        Event and Action Plan for dust impact



Event

ET

IEC

Contractor

Exceedance of Action Level

Exceedance for one sample

       Identify source

       Prepare Notification of Exceedance

       Inform IEC and Contractor

       Repeat measurement to confirm findings

       Increase monitoring frequency to daily if exceedance is due to the Project and continue until the monitoring results reduce to below action level

       Verify the Notification of Exceedance

       Check monitoring data submitted by ET and Contractor's working methods

       Discuss with ET and Contractor on proposed remedial measures

       Rectify any unacceptable practice

       Amend working methods if appropriate

Exceedance for two or more consecutive samples

       Identify source

       Prepare Notification of Exceedance

       Inform Contractor and IEC

       Repeat measurements to confirm findings

       Increase monitoring frequency to daily if exceedance is due to the Project and continue until the monitoring results reduce to below action level

       Discuss with IEC for remedial action required

       Ensure remedial measures are properly implemented

       Continue monitoring at daily intervals if exceedance is due to the Project

        If no exceedance for 3 consecutive days, cease additional monitoring

       Verify the Notification of Exceedance

       Check monitoring data submitted by ET and Contractor's working methods

       Discuss with ET and Contractor on proposed remedial measures

       Review with analysed results submitted by ET

       Review the proposed remedial measures by Contractor

       Supervise the implementation of remedial measures

       Submit proposals for remedial actions to IEC within 3 working days of notification

       Implement the agreed proposals

       Amend proposal if appropriate

 

 

 

Event

ET

IEC

Contractor

Exceedance of Limit Level

Exceedance for one sample

       Identify source

       Prepare Notification of Exceedance

       Inform IEC and Contractor

       Repeat measurement to confirm findings

       Increase monitoring frequency to daily if exceedance is due to the Project and continue until the monitoring results reduce to below limit level

       Assess effectiveness of Contractor's remedial actions and keep EPD and IEC informed of the results

       Verify the Notification of Exceedance

       Check monitoring data submitted by ET and Contractor's working methods

       Discuss with ET and Contractor potential remedial actions

       Supervise the implementation of remedial measures

       Take immediate action to avoid further exceedance

       Submit proposals for remedial actions to IEC within 3 working days of notification

       Implement the agreed proposals

       Amend proposal if appropriate

Exceedance for two or more consecutive samples

       Identify source

       Prepare Notification of Exceedance

       Inform IEC and EPD the causes and actions taken for the exceedances

       Discuss with IEC for remedial action required

       Ensure remedial measures are properly implemented

       Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and informed of the results

       Increase monitoring frequency to confirm findings

       If exceedance stops, cease additional monitoring

       Verify the Notification of Exceedance

       Check monitoring data submitted by ET and Contractor's working methods

       Discuss amongst ET and Contractor on the potential remedial actions.

       Review Contractor's remedial actions whenever necessary to assure their effectiveness

       Supervise the implementation of remedial measures

       Take immediate action to avoid further exceedance

       Submit proposals for remedial actions to IEC of notification

       Implement the agreed proposals

       Resubmit proposals if problem still not under control

       Stop the relevant activity of works until the exceedance is abated


4             Noise Monitoring

4.1         Monitoring Requirement

4.1.1      In accordance with the EM&A manual, noise impact monitoring shall be carried out at 2 monitoring stations NM1 and NM2 once a week during normal construction working hour (0700-1900 Monday to Saturday). The minimum logging interval shall be 30 minutes with average of 6 consecutive Leq 5 mins. L10 and L90 shall also be measured at 5 mins intervals.

4.2         Monitoring Locations, Parameters and Frequency

4.2.1      According to the EM&A Manual, two monitoring stations namely NM1 and NM2 are selected for the impact monitoring.

4.2.2      A baseline monitoring plan has been submitted to IEC and EPD on 31 May 2022 including the proposal with justification of change of monitoring locations. Due to limited access to the original monitoring locations at NM1 and NM2, the adjusted stations at NM1a and NM2a were agreed with IEC prior to the baseline and impact monitoring. The noise monitoring locations are summarized in Table 4-1 and shown in Figure 2. The frequency and duration are shown in Table 4-2.

Table 4-1   Noise Monitoring Locations

Monitoring Station

Representative for

Type of Measurement

NM1a

Wo Keng Shan Tsuen

Free field

NM2a

Lin Ma Hang

Free field

Remarks:

The contractor passed correspondence including original monitoring locations specified on the Approved EM&A Manual to the village representatives on 26 April 2022. After a meeting with Ta Kwu Ling District Rural Committee (RC) Chairman, representative from the RC and a few villagers on 1 May 2022, all the Village Heads of Wo Keng Shan Tsuen, Heung Yuen Wai and Lin Ma Hang verbally refused to accept our proposal for installation of dust and / or noise monitoring equipment within or next to their villages, for the baseline & impact monitoring.

NM1 Wo Keng Shan Tsuen & NM2 Lin Ma Hang are the noise monitoring stations for the construction phase EM&A programme as identified in the approved EM&A Manual for the Project. The access to Tung Lo Hang, Heung Yuen Wai and Wo Keng Shan Tsuen were denied.  A search for alternative noise monitoring locations (NM1a & NM2a) was carried out during the site visit.

The Baseline Monitoring Plan has been submitted to IEC and EPD including the proposal of change of monitoring locations on 31 May 2022. This arrangement was conducted between baseline and impact monitoring and has been agreed by the Independent Environmental Checker (IEC) and no comments received from EPD. Noise measurement at NM1a & NM2a will be considered as free-field and a correction of +3dB(A) would be made to the noise monitoring results.

Due to the adjustment of the location of NM1 & NM2 to NM1a & NM2a, the measured noise levels at NM1 & NM2 would represent the noise levels at NM1 & NM2.

Table 4-2   Noise Monitoring Parameters, Frequency and Duration

Monitoring Station

Parameter

Frequency and Duration

NM1a and NM2a

LAeq (30mins) average of 6 consecutive Leq (5min); L10 (5min) & L90 (5min)

once a week during normal construction working hour (0700-1900 Monday to Saturday)

4.3         Monitoring Results

4.3.1      The impact noise monitoring results are summarized in Table 4-3. The graphical presentations of monitoring data are presented in Appendix E.

Table 4-3   Summary of Noise Monitoring Results during normal working hours (07:00-19:00, Monday to Saturday)

Noise Monitoring Station

Average Leq, 30min, dB(A) (Range)

Action Level

Limit Level

Jul 2023

Aug 2023

Sep 2023

NM1a

62.1

(61.0 – 63.7)

52.5

(51.353.1)

58.3

(56.6 – 59.3)

When one documented complaint is received

>75dB(A)

NM2a

56.3

(54.2 – 58.2)

51.1

(47.354.5)

53.6

(49.8 – 54.7)

Remark:

(1)     * A correction of +3 dB(A) was made to the free field measurements

(2)     If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

4.3.2      No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period. Therefore, there was no record of Notification of Environmental Quality Limits Exceedance in the Appendix F.

4.3.3      No particular observations are identified near the monitoring stations during the monitoring period.

4.4         Recommended Mitigation Measures

4.4.1      The recommended dust mitigation measures from EIA report are listed as followed:

1.     Use of good site practices to limit noise emissions by considering the following:

        Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme;

        Machines and plant (such as trucks, cranes) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

        Plant known to emit noise strongly in one direction, where possible, be orientated so that the noise is directed away from nearby NSRs;

        Silencers or mufflers on construction equipment should be properly fitted and maintained during the construction works;

        Mobile plant should be sited as far away from NSRs as possible and practicable;

        Material stockpiles, mobile container site officer and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.

2.     Select “Quiet plants” which comply with the BS 5228 Part 1 or TM standards.

4.5         Event and Action Plan

4.5.1      Should non-compliance of the criteria occurs, action in accordance with the action plan in Table 4-4 shall be carried out.


Table 4-4 Event and action plan for construction noise monitoring

Event

ET

IEC

Contractor

Exceedance of

Action Level

       Identify source, investigate the causes of exceedance

       Prepare Notification of Exceedance

       Inform IEC and Contractor

       Report the results of investigation to IEC, and Contractor

       Discuss with Contractor and IEC for formulate remedial measures

       Ensure remedial measures are properly implemented

       Have additional monitoring if exceedance is due to the Project. If exceedance stops, cease additional monitoring

       Verify the Notification of Exceedance

       Review the analysed results submitted by ET

       Discuss with ET, and Contractor on the potential remedial actions

       Review the proposed remedial measures

       Supervise the implementation of remedial measures

       Submit noise mitigation proposals to IEC

       Implement the agreed noise mitigation proposals

Exceedance of

Limit Level

       Identify source, investigate the causes of exceedance

       Prepare Notification of Exceedance

       Inform IEC and Contractor

       Repeat measurements to confirm findings

       Discuss with Contractor and IEC for remedial measures

       Ensure remedial measures are properly implemented

       Assess effectiveness of Contractor’s remedial actions and keep IEC and EPD informed of the results

       Have additional monitoring if exceedance is due to the Project. If exceedance stops, cease additional monitoring

       Verify the Notification of Exceedance

       Review the analysed results submitted by ET

       Discuss with ET, and Contractor on the potential remedial actions

       Review the proposed remedial measures

       Supervise the implementation of remedial measures

       Take immediate action to avoid further exceedance

       Submit proposals for remedial actions to IEC of notification

       Implement the agreed proposals

       Resubmit proposals if problem still not under control

       Stop the relevant portion of works as determined by project proponent until the exceedance is abated.

 


5             Water Quality Monitoring

5.1         Groundwater Monitoring

5.1.1    Monitoring Requirement

5.1.1.1   In accordance with the EM&A manual, groundwater quality monitoring shall be carried out at least once per month at the 35 designated groundwater monitoring locations (i.e ED1 to ED35). Based on the existing construction programme, site clearance and site formation works for future landfilling area are in progress. The groundwater monitoring locations ED1 to ED35 will be installed after the site formation work of the landfilling area. No groundwater monitoring is required before the completion of site formation work of the landfilling area.

5.2         Surface Water Monitoring

5.2.1    Monitoring Requirement

5.2.1.1   In accordance with the EM&A manual, impact surface water quality monitoring was carried out at the two designated surface water discharge points (i.e WM1 and WM2) for once per month from commencement of construction works of the Project.

5.2.2    Monitoring Locations, Parameters and Frequency

5.2.2.1   Impact surface water monitoring was carried out at WM1 and WM2. Additional surface water monitoring was carried out at WM2 and GR3 (EPD Monitoring Location). The monitoring locations are indicated in Table 5-1 and Figure 2.

5.2.2.2   The monitoring parameters, frequency and duration of surface water quality monitoring are summarized in Table 5-2. The additional parameters, frequency and duration of surface water quality monitoring are summarized in Table 5-3.

Table 5-1 Surface water quality monitoring locations

Monitoring Station

Location

Coordinates (HK Grid)

Easting

Northing

WM1

Upstream of Lin Ma Hang River

836665

845020

WM2

Ping Yuen River

835592

844186

GR3*

Ping Yuen River

835361

844134

Remarks:

“*” The monitoring location only conducted based on the environmental complaint.

Table 5-2 Surface water quality monitoring Parameters, Frequency and Duration

Parameter

Frequency

pH, Electrical conductivity, DO, Turbidity, SS, Alkalinity, COD, BOD5, TOC, Ammonia-nitrogen, TKN, Nitrate, Sulphate, Sulphite, Phosphate, Chloride, Sodium, Mg, Ca, K, Fe, Ni, Zn, Mn, Cu, Pb, Cd, Coliform Count, Oil and Grease

Once per month

Table 5-3 Additional surface water quality monitoring Parameters, Frequency and Duration

Parameter

Frequency

pH, Electrical conductivity, DO, Turbidity, SS, COD, BOD5, Ammonia-nitrogen, Chloride, Fe, Zn, and Coliform Count

Based on the case of Environmental Complaint

5.2.3    Monitoring Results

5.2.3.1   The summary of monitoring results is presented in Table 5-4, Table 5-5 & Table 5-6. Detailed graphical presentations at each monitoring station of surface water quality (DO, SS and Turbidity) at the monitoring stations are given in Appendix E.
Table 5-4
          Summary of Impact Surface Water Monitoring Results at WM1

Monitoring Parameter(s)

Monitoring Station WM1

Monitoring Results

Action Level

Limit Level

Jul 2023

Aug 2023

Sep 2023

pH

7.2

6.7

7.2

>7.7

>7.8

Electrical Conductivity in μS/cm

99

68

47

---

---

DO in mg/L

7.5

6.5

7.8

<7.4

<4

Turbidity in NTU

6.1

7.4

4.3

>9.2

>9.5

SS in mg/L

2.0

7.2

3.0

>9.7

>11.4

Alkalinity

18

19

11

---

COD

12

6

9

BOD5

<2

<2

<2

TOC

3

<1

2

Ammonia-nitrogen

0.03

0.02

0.04

TKN

0.4

0.2

0.4

Nitrate

0.53

0.05

0.05

Sulphate

7

2

4

Sulphite

<2

<2

<2

Phosphate

0.01

<0.01

0.02

Chloride

7

5

6

Sodium

8350

7740

6340

Mg

660

560

430

Ca

19400

3740

<0.2

K

690

460

680

Fe

780

780

270

Ni

<1

<1

<1

Zn

72

15

14

Mn

72

46

32

Cu

2.0

<1

1

Pb

<1

<1

<1

Cd

<0.2

<0.2

<0.2

Coliform Count

56

68

240

Oil and Grease

<5

<5

<5

Remarks:

“TBC” equal to To Be Confirm


 

Table 5-5          Summary of Impact Surface Water Monitoring Results at WM2

Monitoring Parameter(s)

Monitoring Station WM2

Monitoring Results

Action Level

Limit Level

Jul 2023

Aug 2023

Sep 2023

pH

7.1

6.8

7.2

>7.6

>7.7

Electrical Conductivity in μS/cm

137

133

125

---

---

DO in mg/L

50.2

32.2

7.6

<5

<4

Turbidity in NTU

7.3

7.0

12

>108.3

>108.9

SS in mg/L

16.8

30.8

7.6

>94.7

>94.7

Alkalinity

38

35

31

---

COD

9

7

6

BOD5

<2

<2

<2

TOC

2

<1

2

Ammonia-nitrogen

0.07

0.08

0.13

TKN

0.3

0.4

0.3

Nitrate

0.26

0.24

0.24

Sulphate

13

17

20

Sulphite

<2

<2

<2

Phosphate

<0.01

<0.01

<0.01

Chloride

7

6

4

Sodium

6120

5840

4680

Mg

1330

1480

1290

Ca

15600

16100

<0.2

K

2130

2140

1450

Fe

2370

2710

670

Ni

2.0

4

<1

Zn

26

68

10

Mn

757

1160

563

Cu

2

2

<1

Pb

3

4

1

Cd

<0.2

<0.2

<0.2

Coliform Count

850

290

290

Oil and Grease

<5

<5

<5

Remarks:

“TBC” equal to To Be Confirm

 


 

Table 5-6          Summary of Additional Impact Surface Water Monitoring Results in September 2023

Monitoring Parameter(s)

Monitoring Station

WM2

GR3 (EPD Monitoring Location)

Monitoring Results

Action Level

Limit Level

Monitoring Results

pH

7.5

>7.6

>7.7

7.4

DO in mg/L

7.8

<5

<4

7.6

Turbidity in NTU

8.8

>108.3

>108.9

13.1

Electrical Conductivity in μS/cm

71

---

---

108

SS in mg/L

5.5

>94.5

>94.7

4.9

COD in mg/L

<5

 

6

BOD5 in mg/L

<2

<2

Ammonia-nitrogen in mg/L

2

2

Chloride in mg/L

0.12

0.10

Iron in µg/L

910

670

Zinc in µg/L

13

20

Coliform Count in cfu/100mL

3400

380

Remarks:

“TBC” equal to To Be Confirm

 

5.2.3.2   No exceedance of Action Levels of surface water monitoring was recorded in July 2023.

5.2.3.3   One DO exceedance of Action Level of surface water quality at WM1 was recorded in August 2023. The Notification of Environmental Quality Limits Exceedance is presented in Appendix G. In summary of the investigation, the DO exceedance in Action Level of Surface Water Quality at WM1 may involve the vary of temperature under the hot weather. Therefore, the exceedance is not related to project. No exceedance of Limit Level of surface water monitoring at WM1 was recorded in August 2023. No exceedance of Action Levels and Limit Level of surface water monitoring at WM2 were recorded in August 2023.

5.2.3.4   No exceedance of Action and Limit Levels of surface water monitoring was recorded in September 2023.

5.2.3.5   The Summary of Impact Surface Water Quality Exceedance are shown in Table 5-7. The Notification of Environmental Quality Limits Exceedances will be presented in the report after the investigation.

Table 5-7     Summary of Impact Surface Water Quality Exceedance during the reporting period

Water Quality Monitoring Station

Parameter

pH

DO

Turbidity

SS

Exceedance Count

Level Exceedance

WM1

Action

0

1*

0

0

1*

Limit

0

0

0

0

0

 WM2

Action

0

0

0

0

0

Limit

0

0

0

0

0

Remarks:

(1) # The investigation results will be presented in the report after the investigation.

(2) * equal to non-project related

5.2.4    Recommended Mitigation Measure

5.2.4.1   The recommended surface water mitigation measures from EIA report are listed as followed:

       Channels (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities.

       The overall slope of the site should be kept to a minimum to reduce the erosive potential of surface water flows.

       The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94, which states that the retention time for silts and sediment traps should be 5 minutes under maximum flow conditions.

       All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.

       Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid water quality impacts.

       Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

5.2.5    Event and Action Plan

5.2.5.1   Should non-compliance of the criteria occurs, action in accordance with the action plan in Table 5-8 shall be carried out.


Table 5-8        Event and Action Plan for Water Quality

Event

ET

IEC

Contractor

Action level being exceeded by one sampling day

       Repeat in situ measurement to confirm findings

       Identify source(s) of impact

       Prepare Notification of Exceedance

       Inform IEC and Contractor

       Check monitoring data, all plant, equipment and Contractor’s working methods

       Repeat measurement on next day of exceedance

       Verify Notification of Exceedance

       Check monitoring data and Contractor’s working methods

       Rectify unacceptable practice

       Amend working methods if appropriate

Action level being exceeded by two or more consecutive sampling days

       Repeat in situ measurement to confirm findings

       Identify source(s) of impact

       Prepare Notification of Exceedance

       Inform IEC and Contractor

       Check monitoring data, all plant, equipment and Contractor’s working methods

       Discuss with Contractor and IEC for remedial measures

       Ensure mitigation measures are implemented

       Increase the monitoring frequency to daily until no exceedance of Action level

       Repeat measurement on next day of exceedance

       Verify Notification of Exceedance

       Check monitoring data and Contractor's working method

       Discuss with ET and Contractor on possible remedial actions

       Review the proposed mitigation measures

       Supervise the implementation of mitigation measures

       Submit proposal of additional mitigation measures to IEC of notification

       Implement the agreed mitigation measures

       Amend proposal if appropriate


 

Event

ET

IEC

Contractor

Limit Level being exceeded by one sampling day

       Repeat in situ measurement to confirm findings

       Identify source(s) of impact

       Prepare Notification of Exceedance

       Inform IEC and Contractor;

       Check monitoring data, all plant, equipment and Contractor's working methods

       Discuss mitigation measures with IEC and Contractor

       Ensure mitigation measure are implemented

       Verify Notification of Exceedance

       Check monitoring data submitted By ET and Contractor’s working method

       Discuss with ET and Contractor on possible remedial actions

       Review the proposed mitigation measures

       Supervise the implementation of mitigation measures

       Critically review the working method

       Rectify unacceptable practice

       Take immediate corrective actions to avoid further exceedance

       Submit proposal of mitigation measures to IEC

       Implement the agreed mitigation measures

Limit level being exceeded by two or more consecutive sampling days

       Repeat in situ measurement to confirm findings

       Identify source(s) of impact

       Prepare Notification of Exceedance

       Inform IEC, contractor and EPD

       Check monitoring data, all plant, equipment and Contractor's working methods

       Discuss mitigation measures with IEC and Contractor

       Ensure mitigation measure are implemented

       Verify Notification of Exceedance

       Check monitoring data submitted by ET and Contractor’s working method

       Discuss with ET and Contractor on possible remedial actions

       Review the proposed mitigation measures

       Supervise the implementation of mitigation measures

       Critically review the working method

       Rectify unacceptable practice

       Take immediate corrective actions to avoid further exceedance

       Submit proposal of mitigation measures to IEC

       Implement the agreed mitigation measures

       Resubmit proposals if problem still not under control

       Slow down or to stop relevant activity until exceedance is abated


6       Waste Management

6.1    Wastes generated from this Project include inert construction and demolition (C&D) materials and non-inert C&D materials. Non-inert C&D materials were made up of general refuse, steels and paper/cardboard packaging materials. Steel materials generated from the Project were also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Appendix G.

6.2    The recommended waste management mitigation measures from EIA report are listed as followed:

     Implement a trip-ticket system to ensure that the movement of C&D materials are properly documented and verified in accordance with DEVB TC(W) No. 6/2010.

     Concrete and masonry should be used as general fill and steel reinforcement bars can be used by scrap steel mills.

      Proper areas should be designated for waste segregation and storage wherever site conditions permit.

     Maximise the use of reusable steel formwork to reduce the amount of C&D material.

     Maintain temporary stockpiles and reuse excavated fill material for backfilling and reinstatement.

     On-site sorting and segregation facility of all type of wastes is considered as one of the best practice in waste management and hence, should be implemented in all projects generating construction waste.

     The sorted public fill and C&D waste should be properly reused.

     Excavated slope, stockpiled material and bund walls should be covered by tarpaulin until used in order to prevent wind-blown dust during dry weather, and to reduce muddy runoff during wet weather.


 

7       Landfill Gas Monitoring

7.1   Monitoring Requirement during Construction

Monitoring for Construction Works

7.1.1      Intrinsically safe portable gas detectors should be used during excavation or when working in any confined spaces, which have the potential for presence of LFG and risk of explosion or asphyxiation.  The monitoring equipment should alarm, both audibly and visually, when the concentrations of the following gases were exceeded: 

·         CH4: >10% Lower Explosion Limit (LEL);

·         CO2: >0.5%; and

·         O2: <18% by volume.

7.2   Monitoring Location

7.2.1      During the construction works within the NENT Landfill Extension site with excavation of 1m deep or more, LFG concentrations should be monitored before entry and periodically during the progress of works.  If drilling is required, the procedures for safety management and working procedures as stipulated in EPD’s Landfill Gas Hazard Assessment – Guidance Note should be strictly adopted.

7.2.2      The monitoring frequency and areas to be monitored should be set down prior to commencement of groundworks by the Safety Officer. All measurements in excavations should be made with the monitoring tube located not more than 10mm from the exposed ground surface. Monitoring of excavations should be undertaken as follows:

7.2.3      For excavation works deeper than 1m, measurements should be made:

• at ground surface prior to excavation; 

• immediately before any worker enters the excavation;

• at the beginning of each working day for the entire period the excavation remains open; and 

• periodically through the working day whilst workers are in the excavation.

 

7.2.4      For excavation between 300mm and 1m deep, measurements should be made:

 • directly after the excavation has been completed; and

• periodically whilst the excavation remains open.

 

7.2.5      For excavations less than 300mm deep, monitoring may be omitted, at the discretion of the Safety Officer.

7.2.6      The locations of LFG monitoring locations during reporting period are shown in Table 7-1. The Site formation layout plan is shown in Figure 2 and the Layout of LFG monitoring locations is presented in Figure 3.

Table 7-1          Locations of LFG Monitoring during reporting period

Monitoring Period

Monitoring Location

Type of works

Jul to Sep 2023

Portion A +50 mpD to 70 mpD Platform

Excavation Works

7.3   Monitoring Results

7.3.1      The LFG monitoring was conducted at Portion A +50 mpD to 70 mpD Platform (Conducted on working days) from July to September 2023. The LFG monitoring results are summarized in Table 7-2.

Table 7-2          Summary of LFG Monitoring Results

LFG Monitoring Station

Monitoring Date

Monitoring Parameter(s)

CH4 in %

LEL in %/v

CO2 in %

O2 in %

Average Monitoring Results (Range)

Portion A +50 mpD to 70 mpD Platform

Jul 2023

0

0

0

20.1

(20.020.2)

Aug 2023

0

0

0

20.2

(20.120.4

Sep 2023

0

0

0

20.2

(20.120.2)

Action Level

>10% LEL

---

>0.5%** CO2

<19%

* LEL: Lower Explosive Limit - concentrations in air below which there is not enough fuel to continue an explosion.

** This Limit Level of CO2 at 0.5% is set for reference only, assuming no CO2 emission from a particular location.

7.3.2      No exceedance of Limit Levels of LFG was recorded during the reporting period. Therefore, there was no record of Notification of Environmental Quality Limits Exceedance in the Appendix F.

7.3.3      No effect that arose from the other special phenomena and work progress of the concerned site was noted during the current monitoring month.

7.4   Recommended Mitigation Measures

7.4.1      The recommended landfill gas mitigation measures from EIA report are listed as followed:

 

           Special LFG precautions should be taken due to close proximity of NENT landfill extension site to existing landfill to avoid potential hazards of LFG exposure (ignition, explosion, asphyxiation, toxicity).

           Prominent safety warning signs should be erected on-site to alert all personnel and visitors of LFG hazards during excavation works.

           No smoking or burning should be permitted on-site.

           Prominent 'No smoking' and ‘No Naked Flames’ signs should be erected on-site.

           No worker should be allowed to work alone at any time in excavated trenches or confined areas on-site.

           Adequate fire fighting equipment should be provided on-site.

           Construction equipment should be equipped with vertical exhaust at least 0.6m above ground installed with spark arrestors.

           Electrical motors and extension cords should be explosion-proof and intrinsically safe for use on-site.

           ’Permit to Work' system should be implemented.

           Welding, flame-cutting or other hot works should be conducted only under ‘Permit to Work’ system following clear safety requirements, gas monitoring procedures and presence of qualified persons to supervise the works.

7.5   Event and Action Plan (EAP)

7.5.1      Should non-compliance of the criteria occur, action in accordance with the action plan in Table 7-3 shall be carried out.

Table 7-3 Action Plan for the monitoring during construction phase

Parameter

Monitoring Result

Action

Oxygen (O2)

Action Level <19% O2

Ventilate trench/void to restore O2 to >19%

Limit Level <18% O2

Stop works

Evacuate personnel/prohibit entry

Increase ventilation to restore O2 to >19%

Methane (CH4)

Action Level >10% LEL*

Prohibit hot works

Increase ventilation to restore CH4 to <10% LEL

Limit Level >20% LEL*

Stop works

Evacuate personnel/prohibit entry

Increase ventilation to restore CH4 to <10% LEL

Carbon dioxide

(CO2)

Action Level** >0.5%** CO2

Ventilate to restore CO2 to <0.5%

Limit Level >1.5% CO2

Stop works

Evacuate personnel / prohibit entry

Increase ventilation to restore CO2 to <0.5%

* LEL: Lower Explosive Limit - concentrations in air below which there is not enough fuel to continue an explosion.

** This Action Level of CO2 at 0.5% is set for reference only, assuming no CO2 emission from a particular location.

Depending on the baseline CO2 levels, the Action Level at a particular location will be changed.


 

8       Landscape and Visual

8.1   Monitoring Requirement

8.1.1      In order to monitor the landscape and visual impact after providing mitigation measures effectively, all the specified and affected LCAs, LRs and VSRs should be monitored. Implementation of the mitigation measures during construction phase of the Project has been monitored through the regular site inspection/audit.

8.1.2      All relevant environmental mitigation measures listed in the approved EIA Report and the EM&A Manual, and their implementation status are summarised in Appendix H.

8.2   Result and Observation

8.2.1      Measures to mitigate the landscape and visual impacts during the construction phase has been checked to ensure compliance with the intended aims of the measures within the reporting period. The progress of the engineering works are regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken.

8.2.2      In order to monitor the landscape and visual impact after providing mitigation measures effectively, all the specified and affected LCAs, LRs and VSRs should be monitored. Implementation of the mitigation measures during construction phase of the Project has been monitored through the regular site inspection/audit.


 

9       Cultural Heritage

9.1.1      The Mitigation measures for preservation of the cultural landscape feature located within the project area was conducted before commencement of construction of the project based on the requirement of Survey Report and Mapping Records for Boulder Paths BP1 & 2 & Conditions of G2, G4, G5 G6, G7, G8, G14, G15, G25, G26 and G27 within NENTX.

9.1.2      The survey and mapping works carried out on 25 April 2022 and the verification works carried out on 23 August 22 confirmed that both 2 boulder paths BP1 and BP2 are fall outside the site boundary and the Project area.

9.1.3      All the affected graves within the waste boundary have been removed in accordance with section 119(1) of the Public Health and Municipal Services Ordinance (Cap 132). Removal of the graves as shown on Figure 2 attached to the FEP was proven by the visit of graves on 22 August 2022. All the graves as shown on Figure 2 attached to the FEP were abandoned and removed and no mitigation or preservation measures is necessary.

9.1.4      The Survey Report and Mapping Records for Boulder Paths BP1 & 2 was certified by ET on 10 Oct 2022, was verified by IEC and submitted to EPD on 12 Oct 2022. The Conditions of G2, G4, G5 G6, G7, G8, G14, G15, G25, G26 and G27 within NENTX was certified by ET, was verified by IEC and submitted to EPD on 15 Oct 2022. No later than four weeks before commencement of construction of the project in accordance with Condition 2.4 of the FEP-01/292/2007.

9.1.5      Implementation of the mitigation measures such as permanent fencing to protect the boulder path and setting up warning notices during construction phase of the Project has been monitored through the regular site inspection/audit. The permanent fencing locations are shown in Appendix I. In case of any presence of undiscovered grave during construction phase, AMO will be informed as soon as possible.


 

10   Ecological Monitoring

10.1.1    The post-transplantation monitoring was conducted on 18 Jul, 11 Aug & 15 Sep 2023 based on the requirement of the approved Transplantation Proposal for Plant Species of Conservation Importance (Rev.1). The 12th to 14th Post-transplantation Monitoring and Audit Reports (18th July to 15th September 2023) present the details of requirements, monitoring results and site inspection with photos. During the reporting period, the numbers, measurements, and health conditions of the transplanted plant species are recorded.

10.1.2    In the reporting period, the post-translocation monitoring for the Endemic Freshwater Crab Somanniathelphusa zanklon was conducted on 12 Jul 2023 based on the requirement of the approved Revised Translocation Proposal for the Endemic Freshwater Crab Somanniathelphusa zanklon. The 12th Post-Translocation Monitoring Report (July 2023) presents the details of requirements, monitoring results and site inspection with photos. During the reporting period, no S. zanklon individual is identified.

10.1.3    The details of requirements, monitoring results and site inspection with photos for the post-translocation monitoring and post-transplantation monitoring would be reported separately.

10.1.4    The milestone of the ecological monitoring is presented in Table 10-1. The softcopies of the submissions are provided in https://www.nentx-ema.com/ep-submissions/.


Table 10-1        Milestone of the Ecological Monitoring

Type of Monitoring

Monitoring Event No.

Monitoring Date

Post-transplantation Monitoring

1st

24 Nov 2022

2nd

9 Dec 2022

3rd

21 Dec 2022

4th

13 Jan 2023

5th

26 Jan 2023

6th

8 Feb 2023

7th

24 Feb 2023

8th

20 Mar 2023

9th

21 Apr 2023

10th

12 May 2023

11th

16 Jun 2023

12th

18 Jul 2023

13th

11 Aug 2023

14th

15 Sep 2023

Post-translocation Monitoring

1st (Nov 2022)

24 Nov 2022

2nd (Dec 2022)

9 Dec 2022

3rd (Dec 2022)

21 Dec 2022

4th (Jan 2022)

13 Jan 2023

5th (Jan 2022)

26 Jan 2023

6th (Feb 2023)

8 Feb 2023

7th (Feb 2023)

24 Feb 2023

8th (Mar 2023)

20 Mar 2023

9th (Apr 2023)

21 Apr 2023

10th (May 2023)

12 May 2023

11th (Jun 2023)

11 Jun 2023

12th (Jul 2023)

12 Jul 2023

 


 

11   Site Inspection and Audit

11.1.1    Site Inspection and audits were carried out by ET on weekly basis to monitor the implementation of proper environmental management practices and mitigation measures in the Project Site.

11.1.2    Total 13 weekly environmental site inspections were conducted during the reporting period. 4 of them were the joint environmental site inspections with the representatives of ER, Contractor, IEC and ET. There was no noncompliance recorded during the site inspections.

11.1.3    Details of observations and recommendations are summarized in Table 11-1.

Table 11-1        Observations and Recommendations of Site Audit

Parameter

Date

Observation and Reminders

Follow-up Action Taken

Air Quality

3 Jul 2023

Observation:

Dusty stockpiles in Portion A shall be covered with impervious sheets when they are not in used.

The Contractor was reminded to cover the dusty stockpile with impervious sheets.

31 Jul 2023

Observation:

The slope surface at the Portion E4 shall be coved by impervious sheet.

The contractor was recommended that the exposed slope at the Portion E4 should be covered by impervious sheet. The exposed slope at the Portion E4 should be treated with shotcrete for long term.

31 Jul 2023

Observation:

The assess road at the Portion E4 was dry.

The contractor was advised that the assess road at the Portion E4 should be sprayed with water when the assess road is dry to minimize the dust suppression. The water sprinkler should be considered to establish at the assess road of the Portion E4.

28 Aug 2023

Observation:

The work area in Portion A was dry and dusty.

The contractor was advised to schedule watering in the work area and review the coverage of the water sprinkler.

4 Sep 2023

Observation:

Dust drift was found at the assess road of Portion A when vehicle moving.

The contractor was advised to increase the frequency of water spraying at the assess road of Portion A.

11 Sep 2023

Observation:

The dusty stockpile in SBA should be covered with impervious sheet when the rainfall is forecast.

The Contractor was advised to cover the stockpiles with impervious sheet when they are idle.


 

Parameter

Date

Observation and Reminders

Follow-up Action Taken

Air Quality

18 Sep 2023

Observation:

The demolished tree, shrub or vegetation in Portion B2 should be covered with impervious sheets or placed within a shelter.

The Contractor was reminded to cover the demolished tree, shrub or vegetation with impervious sheets or placed within a shelter.

18 Sep 2023

Observation:

The dry PFA in Portion B2 should be covered entirely with impervious sheets.

The Contractor was reminded to cover dry PFA entirely with impervious sheets.

18 Sep 2023

Observation:

The metal plate at the vehicle entrance in Portion B2 should cover unpaved road surface in Portion B2.

Vehicle entrance should be paved with concrete, bituminous materials, hardcore or metal plates, and kept clear of dusty materials.

18 Sep 2023

Observation:

The main haul road in Portion E4 was dry ad dusty.

The Contractor was advised to schedule watering and recommended to install water sprinklers or mist spray in long term.

25 Sep 2023

Observation:

The main haul road and work site should be wetted regularly to minimize the dust dispersion.

The Contractor was reminded to switch on the water sprinklers along the haul road in SBA and to schedule watering for unpaved haul road and work area. The Contractor has been advised to increase the frequency of watering if necessary under the hot weather condition to minimize dust dispersion.

Noise

No specific observation was identified in the reporting period.

Water Quality

3 Jul 2023

Observation:

Muddy water was observed at the vehicular entrance in Portion A.

The Contractor was reminded to clear the muddy water and divert the muddy water to wastewater treatment facility.

12 Jul 2023

Observation:

The stagnant water, floating leaves, deposited silt and grit were found at the sedimentation basin near the wheel washing facilities at the Portion B1.

The contractor was recommended that the stagnant water should be collected to silt removal facilities for treatment before reusing for wheel washing. The floating leaves, deposited silt and grit should be removed regularly.

12 Jul 2023

Observation:

The exposed slope surfaces were not covered by tarpaulin sheets or treated with shotcrete at the Portion E3-1.

The contractor was recommended to implement the cover works of exposed slope surfaces by tarpaulin sheets or shotcrete at the Portion E3-1 to minimise the potential high concentration construction runoff to silt removal facilities.

 


 

 

Parameter

Date

Observation and Reminders

Follow-up Action Taken

Water Quality

18 Jul 2023

Observation:

The earth bund along the edge of the slope in Portion A was collapsed. The earth bund along the edge of the slope in Portion A should be reconstructed to prevent surface runoff flowing outside the site boundary.

The Contractor was reminded to review the height of the earth bund to ensure the surface runoff should not flow outside the site boundary.

24 Jul 2023

Observation:

Dusty materials was entering in the exist channel in Portion A.

Earth bund or sand barriers shall be provided along the existing channels in Portion A.

24 Jul 2023

Observation:

Earth bund shall be constructed at the edge of the slope to prevent surface runoff flowing outside the site in Portion A.

The contractor was recommended to construction earth bund along the edge of the slope in Portion A.

24 Jul 2023

Observation:

The accumulated silt and grit were found near the sandbags barriers of the Portion E3-1 silt removal facilities.

The contractor was advised that the silt and grit should be removed near the sandbags barriers of the Portion E3-1 silt removal facilities after heavy rain.

24 Jul 2023

Reminder:

The accumulated silt in sedimentation basin Portion E3 shall be removed regularly.

The Contractor was reminded to clear up the accumulated silt regularly to ensure the proper function of the sedimentation basin.

31 Jul 2023

Reminder:

The contractor was reminded that the particular attention should be paid to the control of silty surface runoff during upcoming storm event in accordance with Appendix A2 of ProPECC PN/94.

The contractor was reminded that the particular attention should be paid to the control of silty surface runoff during upcoming storm event in accordance with Appendix A2 of ProPECC PN/94.

31 Jul 2023

Observation:

Earth bunds and ditches should be established at the boundary of the +52 mpd Platform of the Portion A.

The contractor was advised that the earth bunds and ditches should be constructed at the boundary of the +52 mpd Platform of the Portion A. The sandbags barriers or other control of surface runoff measures should be provided at the boundary in short term to avoid the surface runoff flow to the earth bunds at the boundary of the +38 mpd platform directly.

07 Aug 2023

Reminder:

Earth bunds, sand barriers or  alternative shall be provided to prevent sand or silt entering the existing channel through the gaps in Portion A.

The contractor was advised to set up barriers or other measures to prevent sand and silt getting into the channel.

 


 

Parameter

Date

Observation and Reminders

Follow-up Action Taken

Water Quality

07 Aug 2023

Reminder:

The contractor was reminded to ensure the silt removal facility functioning properly in Portion A.

The contractor was reminded that silt removal facility should be checked to ensure that they can function properly.

07 Aug 2023

Observation:

Flocs and fine particles are floating on the water surface in sedimentation tank of the silt removal facility while sand and silt were accumulated in the outlet in Portion E3.

The Contractor was advised to schedule cleaning works for the silt removal facility in Portion E3.

14 Aug 2023

Observation:

The accumulated surface runoff at the lower elevation in Portion D should be diverted to the silt removal facility for wastewater treatment after the rainfall.  

The contractor was advised to pump out the accumulated surface runoff and divert to silt removal facility.

14 Aug 2023

Observation:

Silt was observed in the existing channel at Portion A. The existing channel should be kept away from sand, silt and surface runoff.

The contractor was recommended to construct earth bund with shotcrete along the existing channel in order to prevent surface runoff entering the channel in Portion A.

14 Aug 2023

Observation:

The mixture of silt, sand, rotten leaves and stagnant water in the drip tray should be cleared off after the rainfall.

The contractor was reminded to clear the drip trays after the rainfall.

14 Aug 2023

Observation:

The accumulated silt near the fencing in Portion A should be cleared off before and after rainstorm.

The contractor was advised to clear the accumulated silt near the fencing in Portion A and sedimentation basin in Portion E3 before and after rainstorm.

14 Aug 2023

Observation:

The accumulated silt in the sedimentation basin at Portion E3 should be regularly removed, especially before and after the rainstorm.

The contractor was advised to clear the accumulated silt near the fencing in Portion A and sedimentation basin in Portion E3 before and after rainstorm.

14 Aug 2023

Observation:

The mixture of silt, sand, rotten leaves and stagnant water in the drip tray should be cleared off after the rainfall.

The contractor was reminded to clear the drip trays after the rainfall.

 


 


Parameter

Date

Observation and Reminders

Follow-up Action Taken

Water Quality

14 Aug 2023

Observation:

The silt removal facility was malfunctioned in Portion E3 and flocs are observed on the surface of silt removal facility in both Portion A and Portion E3. The collected wastewater should undergo sufficient mixing to ensure the discharged wastewater should comply with the requirement of WPCO license.

The Contractor has been advised to stop the discharge of wastewater from the malfunctioned silt removal facility immediately. The wastewater should be stored or treated by another silt removal facility temporarily before the original silt removal facility is functioning properly. The Contractor should ensure the discharged wastewater to comply with the requirement of WPCO license.

14 Aug 2023

Observation:

The untreated wastewater was leaked into the channel at Portion E3. The channel should be kept away from untreated wastewater and general waste. 

The contractor was also recommended to increase the number of silt removal facility so as to increase the capacity of wastewater treatment for long term.

14 Aug 2023

Reminder:

The Contractor was reminded to check silt removal facilities, channels and manholes to ensure that they can function properly for the upcoming rainfall in this week.

The contractor was advised to seal the leakage point(s) and place sandbag barriers along the channel to stop the discharge of untreated wastewater in the channel immediately. The accumulated silt and general waste in the channel should be removed. The Contractor has been recommended to review the design of the sedimentation basin to prevent this situation from happening again in the future.

21 Aug 2023

Observation:

Earth bond shall be constructed at the edge of the slope to prevent surface runoff flowing outside the site in Portion A.

The contractor was recommended to construction earth bund along the edge of the slope in Portion A.

28 Aug 2023

Observation:

Dusty materials was entering in the exist channel in Portion A.

Earth bund or sand barriers shall be provided along the existing channels in Portion A.

4 Sep 2023

Observation:

Surface runoff should be intercepted to avoid direct discharge into the channel at Portion E3.

The Contractor should review the effectiveness of setting up sandbag barriers and modify measures to prevent the discharge of surface runoff in both short term and long term. The Contractor was advised to stop the discharge of surface runoff to channel immediately by using any mitigation measures they found appropriate. In long term, the Contractor has been recommended to construct earth bund along the channel to prevent this situation happening again.

 


 


Parameter

Date

Observation and Reminders

Follow-up Action Taken

Water Quality

4 Sep 2023

Observation:

The condition of silt fence in SBA should be reviewed after the heavy rainfall over the few days and should be replaced when it is broken.

The broken or collapsed silt fence should be replaced and properly set up after the heavy rainfall from last week.

25 Sep 2023

Observation:

The exposed slope surface along the channel should be paved to reduce SS level in the wastewater.

The Contractor was recommended to shotcrete the exposed slope surface along the channel to reduce SS level in the wastewater.

25 Sep 2023

Observation:

The accumulated sand or silt in the outlet of the silt removal facility at Portion A should be removed.

The Contractor was advised to clear the accumulated sand or silt in the outlet of the silt removal facility at Portion A.

Waste and Chemical Management

3 Jul 2023

Observation:

Chemical containers in SBA shall be stored properly to prevent any potential of chemical leakage and generation of chemical waste.

The contractor has been reminded to provide proper chemical storage area on site.

12 Jul 2023

Observation:

Full loading of the rubbish skips for general waste at the Portion D and lack of waste separation were found.

The contractor was recommended that accumulation of waste should be avoid, the waste should be disposed regularly & the general waste should be collected properly by using the waste separation facilities for paper, aluminium cans and plastic bottles etc.

12 Jul 2023

Observation:

The high amount of deposited silt was found at the silt removal facilities at the Portion E3-1.

The contractor was advised that the deposited silt should be removed and regularly and increase the checking frequency of it, and the silt removal facilities should be maintained at good condition to maintain the high effectiveness of it.

18 Jul 2023

Observation:

The stagnant water in the drip trays should be cleared off In Portion A.

The Contractor was reminded to clear the drip tray after the rainfall.

07 Aug 2023

Observation:

The mixture of silt and stagnant water in the drip tray should be cleared off in Portion E3.

The contractor was recommended to clear the drip tray.

 


 

Parameter

Date

Observation and Reminders

Follow-up Action Taken

Waste and Chemical Management

14 Aug 2023

Observation:

Oil drums in SBA are observed without drip tray.

Drip tray should be provided to the oil drums and all chemical container in the site.

21 Aug 2023

Observation:

The mixture of silt and stagnant water in the drip tray should be cleared off in Portion E3.

The contractor was reminded to clear the drip tray.

21 Aug 2023

Observation:

Enclosed bins or compaction units should be provided to separate general waste with chemical waste and construction waste in Portion A.

The contractor was recommended to provide enclosed bins or compaction units in Portion A.

21 Aug 2023

Observation:

Chemical containers should be placed within the drip trays in Portion E4.

The contractor was reminded to provide drip tray for all chemical containers.

4 Sep 2023

Observation:

Over loading of accumulated waste was found at the waste skip of Portion D.

The contractor was recommended to increase the frequency of waste collection and the amount of waste skip to avoid over loading condition of waste skip at Portion D.

18 Sep 2023

Observation:

General refuse and non-inert waste should be stored in enclosed bins or compaction unit.

General waste generated on-site should be stored in enclosed bins or compaction units separately from the construction and chemical wastes.

18 Sep 2023

Observation:

Empty chemical containers in Portion E3 should be properly stored before the disposal.

The Contractor was reminded to properly store empty chemical container before disposal.

25 Sep 2023

Observation:

Chemical spillage was observed at Portion E4 and chemical containers should be placed on the drip tray.

The Contractor was reminded to dispose chemical waste and provide drip tray for all chemical containers.

Landscape and Visual Impact

No specific observation was identified in the reporting period.

Permit / Licenses

No specific observation was identified in the reporting period.

 

11.1.4    Five general site inspection on 31 July, 4 & 21 August 2023, and 7 & 13 September 2023 were conducted by Environmental Protection Department-Regional Office (North) (EPD-RNG).

 

12   Environmental Non-conformance

12.1      Summary of Monitoring Exceedance

Air Quality, Noise & Landfill Gas Monitoring

12.1.1    No Action / Limit Level exceedance impact monitoring was recorded at designated monitoring stations during the reporting period.

12.1.2    The Summary of Impact 1-hr & 24-hr TSP Exceedance are shown in Table 12-1.

Table 12-1        Summary of Impact 1-hr & 24-hr TSP Exceedance during the reporting period

Dust Monitoring Station

Parameter

1-hr TSP

Exceedance Count

Accumulate of project

24-hr TSP

Exceedance Count

Accumulate of project

Level Exceedance

AM1

Action

0

0

0

0

0

2*

Limit

0

0

0

0

0

3*

 AM2

Action

0

0

0

0

0

0

Limit

0

0

0

0

0

0

AM3

Action

0

0

0

0

0

4*

Limit

0

0

0

0

0

3*

Remarks: * equal to non-project related

Surface Water Quality Monitoring

12.1.3    No exceedance of Action Levels of surface water monitoring was recorded in July 2023.

 

12.1.4    One DO exceedance of Action Level of surface water quality at WM1 was recorded in August 2023. The Notification of Environmental Quality Limits Exceedance is presented in Appendix G. In summary of the investigation, the DO exceedance in Action Level of Surface Water Quality at WM1 may involve the vary of temperature under the hot weather. Therefore, the exceedance is not related to project. No exceedance of Limit Level of surface water monitoring at WM1 was recorded in August 2023. No exceedance of Action Levels and Limit Level of surface water monitoring at WM2 were recorded in August 2023.

 

12.1.5    No exceedance of Action and Limit Levels of surface water monitoring was recorded in September 2023.

 

12.1.6    The Summary of Impact Surface Water Quality Exceedance are shown in Table 12-2

 


 

Table 12-2   Summary of Impact Surface Water Quality Exceedance during the reporting period

Water Quality Monitoring Station

Parameter

pH

DO

Turbidity

SS

Exceedance Count

Level Exceedance

WM1

Action

0

1*

0

0

1*

Limit

0

0

0

0

0

 WM2

Action

0

0

0

0

0

Limit

0

0

0

0

0

Remarks:

(1) # The investigation results will be presented in the report after the investigation.

(2) * equal to non-project related

12.2      Summary of Environmental Non-compliance

12.2.1    One warning regarding suspected non-compliance event with Condition 1.7 and 2.15(a) of the EP & Condition 1.7 and 2.13(a) of the FEP-01 & FEP-02 was recorded during the reporting period. The related rectified actions are being taken in progress by the contractor.

12.3      Summary of Environmental Complaint

12.3.1    No environmental complaint was recorded from July 2023.

12.3.2    One complaint received from EPD-RNG on 3 August 2023 and another one complaint received from EPD-RNG on 18 August 2023 were recorded in August 2023. The complaint on 3 August 2023 & complaint on 18 August 2023 were investigated by related parties.

 

12.3.3    One complaint received from EPD-RNG on 14 September 2023 was recorded in September 2023. The complaint on 14 September 2023 was investigated by related parties.

 

Environmental Complaint on 3 August 2023

12.3.4    The complaint about the water aspect was received by ET on 3 August 2023 at 17:45 via EPD-RNG email. The main content of the complaint mentioned the muddy water was observed at River Ganges (GR3) (Water Quality Monitoring Point from EPD). In summary of the investigation, the muddy water caused from multi-potential sources while the runoff from the box culvert under the Wo Keng Shan Road is the major source including runoff from Existing channel near Portion E3-1, discharge water from the silt removal facilities at Portion E3-1 of the project, runoff from branch near the entrance of Portion E3-1, runoff from weighting plaza of NENT Landfill & natural stream near Wo Keng Shan & Shui Ngau Tso etc.. Hence, the project is a part of factor causing the high turbidity muddy water. To minimise the potential impact of construction runoff from the project, the further mitigation measures and enhancement of the temporary surface water drainage system were advised to implement by contractor.

 

Environmental Complaint on 18 August 2023

12.3.5    The complaint about the water aspect was received by ET on 18 August 2023 at 16:51 via EPD-RNG email. The main content of the complaint mentioned the muddy water was observed at River Ganges (GR3) (Water Quality Monitoring Point from EPD). In summary of the investigation, the complaint is project related. It viewed that muddy water arising from wheel washing water from the site entrance at Portion E4 & Runoff from Existing Channel near Portion E3-1 & discharge water from the silt removal facilities at Portion E3-1 eventually flows into the box culvert under Wo Keng Shan Road, WM2 and ultimately to GR3. The related rectified actions should be conducted by the contractor as soon as possible.

 

Environmental Complaint on 14 September 2023

12.3.6    The complaint about the water aspect was received by ET on 14 September 2023 at 17:17 via EPD-RNG email. The main content of the complaint mentioned the muddy water was observed at River Ganges (GR3) (Water Quality Monitoring Point from EPD). In summary of the investigation, the complaint is project related. It viewed that muddy water arising from wheel washing water from the site entrance at Portion E4 & Runoff from Existing Channel near Portion E3-1 & discharge water from the silt removal facilities at Portion E3-1 eventually flows into the box culvert under Wo Keng Shan Road, WM2 and ultimately to GR3. The related rectified actions should be conducted by the contractor as soon as possible.

12.3.7    The cumulative statistics on environmental complaints are presented in Table 12-3.

Table 12-3 Cumulative Statistics on Environmental Complaints

Reporting Period  

Environmental Aspects

No. of Environmental Complaints

Air Quality

Noise

Water Quality

Waste

Ecology

Jul 2023

0

0

0

0

0

0

Aug 2023

0

0

2

0

0

0

Sep 2023

0

0

1

0

0

0

Total

0

0

3

0

0

0

Accumulate of project

1*

0

5(1*)

0

0

6(2*)

Remarks:

(1)   * equal to non-project related after the investigation

(2)   # equal to the investigation results will be presented in the report after the investigation.

12.3.8    Cumulative complaint / enquiry log, Summaries of complaints and enquiries & Environmental complaint reports are presented in Appendix J. The investigation results will be presented when the investigation was finished.

12.4      Summary of Environmental Summons and Successful Prosecution

12.4.1    No summons and prosecution were received during the reporting period


 

13   Implementation Status on Environmental Mitigation Measures

13.1.1    The Contractor has generally implemented part of environmental mitigation measures and requirements as stated in the EIA Report, the EP and EM&A Manual and the contract documents. The implemented mitigation measures are considered effective. The implementation status during the reporting period is summarized in Appendix H.


 

14   Conclusion

14.1.1    1-hr & 24-hr TSP impact monitoring was carried out in the reporting month. No Action / Limit Level exceedance for 1-hr & 24-hr TSP impact monitoring at AM1, AM2 & AM3 was recorded during the period.

14.1.2    Construction noise monitoring was carried out in the reporting month. No Action / Limit Level exceedance at NM1a & NM2a was recorded during the period.

14.1.3    Site clearance of future landfilling area is in progress. The installation of groundwater monitoring boreholes will be installed after the site formation work of the landfilling area. The target commencement period of groundwater monitoring will be in 2026. No groundwater monitoring is required before the completion of site formation work of the landfilling area.

14.1.4    Surface water monitoring was carried out in the reporting month. No exceedance of Action Levels of surface water monitoring was recorded in July 2023. One DO exceedance of Action Level of surface water quality at WM1 was recorded in August 2023. In summary of the investigation, the DO exceedance in Action Level of Surface Water Quality at WM1 may involve the vary of temperature under the hot weather. Therefore, the exceedance is not related to project. No exceedance of Limit Level of surface water monitoring at WM1 was recorded in August 2023. No exceedance of Action Levels and Limit Level of surface water monitoring at WM2 were recorded in August 2023. No exceedance of Action and Limit Levels of surface water monitoring was recorded in September 2023.

14.1.5    Landfill Gas Monitoring was carried out in the reporting month. No exceedance of Limit Levels of LFG was recorded during the reporting period.

14.1.6    In terms of cultural heritage, implementation of the mitigation measures such as permanent  fencing to protect the boulder path and setting up warning notices during construction phase of the Project has been monitored through the regular site inspection/audit in the reporting period. All the mitigation measures are in order.

14.1.7    Post-translocation Monitoring was carried out in the reporting period. No S. zanklon individual was found. Post-transplantation monitoring was carried out in the reporting period. The numbers, measurements and health conditions of the transplanted species are recorded.

14.1.8    13 environmental site inspections were carried out in the reporting month. Recommendations on mitigation measures for Permit/ Licenses were given to the Contractor for remediating the deficiencies identified during the site inspections.

14.1.9    No environmental complaint was recorded from July 2023. One complaint received from EPD-RNG on 3 August 2023 and another one complaint received from EPD-RNG on 18 August 2023 were recorded in August 2023. For the complaint from EPD-RNG on 3 August 2023, the further mitigation measures and enhancement of the temporary surface water drainage system were advised to implement by contractor. For the complaint received from EPD-RNG on 18 August 2023, the related rectified actions should be conducted by the contractor as soon as possible. One complaint received from EPD-RNG on 14 September 2023 was recorded in September 2023. The related rectified actions should be conducted by the contractor as soon as possible.

14.1.10  One warning regarding suspected non-compliance event with Condition 1.7 and 2.15(a) of the EP & Condition 1.7 and 2.13(a) of the FEP-01 & FEP-02 was recorded during the reporting period. The related rectified actions are being taken in progress by the contractor.

14.1.11  No notification of summons and prosecution was received during the reporting period.


 

Comment and Recommendations

14.1.12  The recommended environmental mitigation measures, as proposed in the EIA reports and EM&A Manuals shall be effectively implemented to minimize the potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental impacts generated from the construction activities and ensure the proper implementation of mitigation measures.

14.1.13  According to the environmental audit performed in the reporting period, the following recommendations were made:

Air Quality Impact

         The Contractor was reminded to cover the dusty stockpile with impervious sheets.

         The Contractor was recommended that the exposed slope should be covered by impervious sheet. The exposed slope should be treated with shotcrete for long term.

         The Contractor was advised that the assess road should be sprayed with water when the assess road is dry to minimize the dust suppression. The water sprinkler should be considered to establish at the assess road.

         The Contractor was advised to schedule watering in the work area and review the coverage of the water sprinkler.

         The Contractor was advised to increase the frequency of water spraying at the assess road.

         The Contractor was advised to cover the stockpiles with impervious sheet when they are idle.

         The Contractor was reminded to cover the demolished tree, shrub or vegetation with impervious sheets or placed within a shelter.

         The Contractor was reminded to cover dry PFA entirely with impervious sheets.

         Vehicle entrance should be paved with concrete, bituminous materials, hardcore or metal plates, and kept clear of dusty materials.

 

Construction Noise Impact

         No specific observation was identified in the reporting period.

Water Quality Impact

         The Contractor was reminded to clear the muddy water and divert the muddy water to wastewater treatment facility.

         The Contractor was recommended that the stagnant water should be collected to silt removal facilities for treatment before reusing for wheel washing. The floating leaves, deposited silt and grit should be removed regularly.

         The Contractor was recommended to implement the cover works of exposed slope surfaces by tarpaulin sheets or shotcrete to minimise the potential high concentration construction runoff to silt removal facilities.

         The Contractor was reminded to review the height of the earth bund to ensure the surface runoff should not flow outside the site boundary.

         The Contractor was recommended to construction earth bund along the edge of the slope.

         The Contractor was advised that the silt and grit should be removed near the sandbags barriers of the Portion E3-1 silt removal facilities after heavy rain.

         The Contractor was reminded that the particular attention should be paid to the control of silty surface runoff during upcoming storm event in accordance with Appendix A2 of ProPECC PN/94.

 

         The Contractor was advised that the earth bunds and ditches should be constructed at the boundary of the +52 mpd Platform of the Portion A. The sandbags barriers or other control of surface runoff measures should be provided at the boundary in short term to avoid the surface runoff flow to the earth bunds at the boundary of the +38 mpd platform directly.

         The Contractor was reminded that silt removal facility should be checked to ensure that they can function properly.

         The Contractor was advised to pump out the accumulated surface runoff and divert to silt removal facility.

         The Contractor was reminded to clear the drip trays after the rainfall.

         The Contractor was advised to clear the accumulated silt near the fencing in Portion A and sedimentation basin in Portion E3 before and after rainstorm.

         The Contractor was recommended to construction earth bund along the edge of the slope in Portion A.

         Earth bund or sand barriers shall be provided along the existing channels in Portion A.

         The Contractor should review the effectiveness of setting up sandbag barriers and modify measures to prevent the discharge of surface runoff in both short term and long term. The Contractor was advised to stop the discharge of surface runoff to channel immediately by using any mitigation measures they found appropriate. In long term, the Contractor was recommended to construct earth bund along the channel to prevent this situation happening again.

         The broken or collapsed silt fence should be replaced and properly set up after the heavy rainfall from last week.

         The Contractor was advised to reconstruct the demolished sedimentation basin to act as silt trap and to achieve 5 minutes of retention time under maximum flow condition.

         The Contractor was recommended to shotcrete the exposed slope surface along the channel to reduce SS level in the wastewater.

         The Contractor was advised to clear the accumulated sand or silt in the outlet of the silt removal facility at Portion A The Contractor has been advised to stop the discharge of wastewater from the malfunctioned silt removal facility immediately. The wastewater should be stored or treated by another silt removal facility temporarily before the original silt removal facility is functioning properly. The Contractor should ensure the discharged wastewater to comply with the requirement of WPCO license.

         The Contractor was also recommended to increase the number of silt removal facility so as to increase the capacity of wastewater treatment for long term.

         The Contractor was advised to seal the leakage point(s) and place sandbag barriers along the channel to stop the discharge of untreated wastewater in the channel immediately. The accumulated silt and general waste in the channel should be removed. The Contractor has been recommended to review the design of the sedimentation basin to prevent this situation from happening again in the future.

 

Waste and Chemical Management

         The Contractor has been reminded to provide proper chemical storage area on site.

         The Contractor was recommended that accumulation of waste should be avoid, the waste should be disposed regularly & the general waste should be collected properly by using the waste separation facilities for paper, aluminium cans and plastic bottles etc.

         The Contractor was advised that the deposited silt should be removed and regularly and increase the checking frequency of it, and the silt removal facilities should be maintained at good condition to maintain the high effectiveness of it.

         The Contractor was reminded to clear the drip tray after the rainfall.

         Drip tray should be provided to the oil drums and all chemical container in the site.

         The contractor was recommended to provide enclosed bins or compaction units in Portion A.

         The contractor was recommended to increase the frequency of waste collection and the amount of waste skip to avoid over loading condition of waste skip at Portion D.

         General waste generated on-site should be stored in enclosed bins or compaction units separately from the construction and chemical wastes.

         The Contractor was reminded to properly store empty chemical container before disposal.

         The Contractor was reminded to dispose chemical waste and provide drip tray for all chemical containers.

 

Landscape and Visual Impact

         No specific observation was identified in the reporting period.

 

Permit / Licenses

         No specific observation was identified in the reporting period.

 

14.1.14  The Contractor has generally implemented environmental mitigation measures and requirements as stated in the EIA Report, the EP and EM&A Manual and the contract documents. The implemented mitigation measures are considered effective.

14.1.15  The ET will keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.