Agreement No. CE 20/2004(EP) North East
New Territories (NENT) Landfill Extension Quarterly Environmental Monitoring and Audit
Report (No. 7) – July to September 2024 |
Contents
12 Environmental Non-conformance
13 Implementation Status on Environmental Mitigation
Measures
Figure
Location of the Project Site |
|
Impact Monitoring Locations |
|
Landfill Gas Monitoring Locations |
Appendix
Construction Programme & Construction Site Activities |
|
Project Organization Chart & Management Structure |
|
Detail Status of FEP & EP Submission |
|
Graphical Presentations |
|
Notification of Environmental Quality Limits Exceedance |
|
Waste Flow Table |
|
Environmental Mitigation Implementation Schedule (EMIS) |
|
Mitigation Measures of Cultural Landscape Features |
|
Cumulative complaint / enquiry log and Summaries of complaints and enquiry |
ES1. Aurecon Hong Kong Limited (Aurecon) was appointed to undertake the role of Environmental Team (ET) and carry out Environmental Monitoring and Audit for the North East New Territories (NENT) Landfill Extension.
ES2. The construction phase and EM&A programme of the Project commenced on 1 December 2022.
ES3. This 7th Quarterly EM&A Report presents the EM&A works conducted from 1 July to 30 September 2024 in accordance with the Updated EM&A Manual.
Summary
of Construction Works undertaken during Report Period
ES4. The major construction works undertaken during the reporting period include:
ES Table1
Major Construction Works undertaken during
the Reporting Period
Reporting Month |
|||
Jul 2024 |
Aug 2024 |
Sep 2024 |
|
- Material
loading and unloading, site traffic
at Portion A, SBA to alternative disposal ground |
✓ |
✓ |
✓ |
- Construction of site buildings at Portion D |
✓ |
✓ |
✓ |
- Site
clearance
at Portion A, B2/E1, E3-1 & E4 |
✓ |
✓ |
✓ |
- Installation of
permanent fencing at Portion A, B1 & E4 |
✓ |
✓ |
✓ |
- Site
formation
at Portion A, B2/E1, E3-1 & E4 |
✓ |
✓ |
✓ |
- Tree
felling
at whole site |
✓ |
✓ |
✓ |
Shotcreting (Permanent
and Temporary) at whole site |
✓ |
✓ |
✓ |
Soil nail installation
at Portion A, B2/E1 & E4 |
✓ |
✓ |
✓ |
Environmental
Exceedance
Air Quality, Noise,
Surface Water Quality & Landfill Gas Monitoring
ES5. No exceedance of the Action and Limit Levels were recorded at designated monitoring stations during the reporting period.
Environmental
Non-conformance/Compliant/Summons and Prosecution
ES6. No non-conformance event, complaint, summons/prosecutions were recorded and received in this reporting period.
1.1 Background
1.1.1 The North East New Territories Landfill Extension (the NENTX Project) is located adjacent to the existing North East New Territories (NENT) Landfill at Ta Kwu Ling. The extension site is located in a valley covering mainly the existing NENT Landfill Stockpile and Borrow Area that was formed to the east of the existing landfill as part of the original site development of the landfill, and layout plan shown in Figure 1.
1.1.2 The NENTX is a designated project. The Environmental Impact Assessment (EIA) Report (AEIAR-111/2007) and an Environmental Monitoring and Audit (EM&A) Manual were approved on 20 September 2007. The project is governed by an Environmental Permit (EP) (EP-292/2007) which was granted on 26 November 2007. A further of EP (FEP) was applied and the FEP (FEP-01/292/2007) was subsequently granted on 28 April 2022. Another further of EP (FEP-02/292/2007) was subsequently granted on 23 August 2023. The Updated EM&A Manual was approved by Director of Environmental Protection (DEP) on 4 January 2024.
1.1.3 In accordance with the requirements specified in Section 2.7 to 2.11 and Section 12.3 of the Updated EM&A Manual, Quarterly EM&A report should be submitted to the DEP within 10 working days after the end of the reporting quarter. The submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC).
1.1.4 The construction phase and EM&A programme of the Project commenced on 1 December 2022.
1.2 Nature, Scale and Scope of the captioned Designated Project
1.2.1 The Nature, Scale and Scope of the captioned Designated Project is presented in Table 1-1.
Table 1-1 Nature, Scale and Scope of the captioned
Designated Project
Item(s) |
Content |
Nature of Designated
Project |
Construction and operation of a landfill for waste as defined in the
“Waste Disposal Ordinance” (Cap. 354) |
Scale and Scope of Designated Project |
The Project mainly consists of the followings: - Construction and operation of a landfill extension of about 70 hectares
with a target void space of at least 19 million cubic metres on the eastern
side of the existing NENT Landfill, including the followings: - i.
Site formation and
preparation; ii. Installation of liner system; iii. Installation of leachate collection, treatment and disposal facilities; iv. Installation of gas collection, utilization and management facilities; v. Utilities provisions and drainage diversion; vi. Landfilling operation; vii. Restoration and aftercare in subsequent stages; and viii.
Measures to mitigate
environmental impacts as well as environmental monitoring and auditing to be
implemented. |
1.3 Purpose of this Report
1.3.1 This is the 7th Quarterly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from 01 July to 30 September 2024.
1.4.1 The structure of the report is as follows:
-
details the background, purpose and structure of the report.
Section 2 – Project Information
-
summarises background and scope of the Project, site description, project
organization and contact details, construction programme, the construction
works undertaken and the status of Environmental Permit(s)/License(s) during
the reporting period.
Section 3 – Air Quality Monitoring
Section 5 – Water Quality Monitoring
Section 6 – Waste Management
Section
7 – Landfill Gas Monitoring
Section 8 – Landscape and Visual
Section 10 – Ecological Monitoring
Section 11 – Site Inspection and Audit
Section 12 – Environmental Non-Conformance
Section 13 – Implementation Status on Environmental Mitigation Measures
Section 14 – Conclusion
2.1.1 A summary of the major construction activities undertaken in this reporting period is shown in Table 2-1. Construction programme and detailed construction activities are illustrated in Appendix A.
Table 2-1 Major
Construction Activities Undertaken in the Reporting Period
Construction Activities
Undertaken |
Reporting Month |
||
Jul 2024 |
Aug 2024 |
Sep 2024 |
|
- Material
loading and unloading, site traffic at Portion A, SBA to
alternative disposal ground |
✓ |
✓ |
✓ |
- Construction of site
buildings at Portion D |
✓ |
✓ |
✓ |
- Site
clearance at Portion A, B2/E1,
E3-1 & E4 |
✓ |
✓ |
✓ |
- Installation of
permanent fencing at Portion A, B1 & E4 |
✓ |
✓ |
✓ |
- Site
formation at Portion A, B2/E1,
E3-1 & E4 |
✓ |
✓ |
✓ |
- Tree
felling at whole site |
✓ |
✓ |
✓ |
Shotcreting
(Permanent and Temporary) at whole site |
✓ |
✓ |
✓ |
Soil
nail installation at Portion A, B2/E1 & E4 |
✓ |
✓ |
✓ |
2.2 Project Organization & Management Structure
2.2.1 The Project Organization Chart & Management Structure are shown in Appendix B. The key personnel contact information is summarized in Table 2-2.
Table 2-2 Contact Information of Key Personnel
Party |
Name |
Contact
Number |
Contractor (Veolia Hong Kong Holding Ltd.) |
Mr. Matt Choy |
2902 5296 |
Independent
Environmental Checker (IEC) (Meinhardt Infrastructure
and Environment Ltd.) |
Ms. Claudine Lee |
2859 5409 |
Environmental Team Leader
(ETL) (Aurecon Hong Kong
Limited) |
Mr. Fredrick Leong |
3664 6888 |
2.3 Status of Submission required under the FEP & EP during reporting period
2.3.1 The status of statutory environmental compliance with the EP & FEP conditions under the EIAO, submission status under the EP & FEP during reporting period are presented in Table 2-3. The detail status of statutory environmental compliance with the EP & FEP conditions under the EIAO, submission status under the EP & FEP for NENTX project are shown in Appendix C.
Table 2-3 Status of
Submissions required under the EP & FEP during reporting period
EP
Condition |
FEP
Condition |
Submission / Measures |
Status |
2.3 |
2.1 |
Management Organization of Main Construction
Companies |
Submitted |
2.4 |
2.2 |
Setting up of Community Liaison Group
(CLG) |
Community Liaison Group
was set up. |
2.5 |
2.3 |
Submission of EM&A Manual |
Submitted |
2.6 |
2.4 |
Submission of Preservation of Cultural
Landscape Features |
Submitted |
2.7 |
2.5 |
Submission of Vegetation Survey
(Transplantation Proposal) |
Submitted |
2.8 |
2.6 |
Submission of Translocation Proposal |
Submitted |
2.9 |
2.7 |
Submission of Transplantation Report
and Post-Transplantation Monitoring |
Submitted |
2.10 |
2.8 |
Submission of Translocation Report and
Post-Translocation Monitoring |
Submitted |
2.11 |
2.9 |
Submission of Detailed Landfill Gas
Hazard Assessment Report |
Submitted |
2.12 |
2.10 |
Submission of Waste Management Plan |
Submitted |
3.2 |
3.2 |
Submission of Baseline Monitoring Report |
Submitted |
3.3 |
3.3 |
Submission of Monthly EM&A Report |
20th report (Jul
2024) 21st report (Aug
2024) 22nd report (Sep
2024) |
2.4 Status of Environmental Approval Document
2.4.1 A summary of the relevant valid permits, licences, and/or notifications on environmental protection for this Project since the granting of the EP & FEP is presented in Table 2-4.
Reference |
Expiry
Date |
Remark |
|
Environmental Permit (EP) |
EP-292/2007 |
Throughout the Contract |
Permit granted on 26 November 2007 |
Further Environmental Permit (FEP) |
FEP-01/292/2007 |
Throughout the Contract |
Permit granted on 28 April 2022 |
FEP-02/292/2007 |
Throughout the Contract |
Permit granted on 23
August 2023 |
|
Notification of Construction
Works as required under Air Pollution Control (Construction Dust) Regulation |
479809 |
Throughout the Construction
Phase |
Notified on 13 May 2022 |
Registration of Waste Producer
under Waste Disposal Ordinance |
7043692 |
Throughout the Contract |
Registered on 13 April 2022 |
Construction Noise Permit |
GW-RN0702-24 |
18 September 2024 |
Permit granted on 17 June 2024 |
GW-RN1050-24 |
18 December 2024 |
Permit granted on 6 September 2024 |
|
Registration as Chemical Waste
Producer |
5213-642-P1034-18 |
Throughout the Contract |
Registered on 11 July 2022 |
Effluent Discharge License
under Water Pollution Control Ordinance |
WT00042301-2022 |
31 October 2027 |
Permit granted on 18 October 2022 Variation
of Licence (Permit granted on 7 February 2023) |
3.1.1.1
In accordance with the Updated EM&A Manual, 1-hr & 24-hr Total Suspended Particulates (TSP) levels
should be measured at the designated air quality monitoring stations in every 6
days to ensure that any deteriorating air quality could be readily detected,
and timely action shall be undertaken to rectify such situation. For 1-hr TSP
monitoring, the sampling frequency of at least three times in every six-days
should be undertaken when the highest dust impact occurs. The specific time to
start and stop the 24- hr TSP monitoring shall be clearly defined for each
location.
3.1.2 Monitoring Parameters, Frequency and Location
3.1.2.1
According to the Updated EM&A
Manual, three monitoring stations namely AM(D)1, AM(D)2 and AM(D)3 are selected
for the impact monitoring.
3.1.2.2 A baseline monitoring plan has been submitted to IEC and EPD on 31 May 2022 including the proposal with justification of change of monitoring locations. Due to limited access to the original monitoring locations at AM(D)1, AM(D)2 and AM(D)3, the adjusted stations at AM1, AM2 and AM3 were agreed with IEC prior to the baseline and impact monitoring. The locations of adjusted dust monitoring locations are shown in Figure 2.
3.1.2.3 The locations of dust monitoring stations are shown in Table 3-1. The monitoring parameters, frequency and duration are shown in Table 3-2.
Table 3-1 Locations of Dust Monitoring Stations
Monitoring Station |
Representative for |
Monitoring Parameters |
|
AM1 |
Tung Lo Hang |
1-hr and
24-hr TSP |
|
AM2 |
Heung Yuen Wai |
1-hr and 24-hr TSP |
|
AM3 |
Wo Keng Shan Tsuen |
1-hr and
24-hr TSP |
Remarks:
The contractor passed
correspondence including original monitoring locations specified on the Approved
EM&A Manual to the village representatives on 26 April 2022. After a
meeting with Ta Kwu Ling District Rural Committee (RC) Chairman, representative
from the RC and a few villagers on 1 May 2022, all the Village Heads of Wo Keng
Shan Tsuen, Heung Yuen Wai and Lin Ma Hang verbally refused to accept our
proposal for installation of dust and / or noise monitoring equipment within or
next to their villages, for the baseline & impact monitoring.
AM(D)1 Tung Lo
Hang, AM(D)2 Heung Yuen Wai, AM(D)3 Wo Keng Shan Tsuen are the air monitoring
stations for the construction phase EM&A programme as identified in the
approved EM&A Manual for the Project. The access to Tung Lo Hang, Heung
Yuen Wai and Wo Keng Shan Tsuen were denied.
A search for alternative air monitoring locations (AM1, AM2 & AM3)
was carried out during the site visit.
The Baseline
Monitoring Plan has been submitted to IEC and EPD including the proposal of
change of monitoring locations on 31 May 2022. This arrangement was conducted
between baseline and impact monitoring and has been agreed by the Independent
Environmental Checker (IEC) and no comment received from EPD.
Due to the
adjustment of the location of AM(D)1, AM(D)2 & AM(D)3to AM1, AM2 & AM3,
the measured air quality levels at AM1, AM2 & AM3 would represent the air
quality levels at AM(D)1, AM(D)2 & AM(D)3.
Table 3-2 Dust Impact Monitoring Parameters,
Frequency and Duration
Monitoring
Station |
Parameter |
Frequency and Duration |
AM1, AM2, AM3 |
1-hr TSP |
At least 3 times per 6 days |
24-hr TSP |
1 time per 6 days |
3.1.3.1 The impact dust monitoring results are summarized in Table 3-3 and Table 3-4. The graphical presentations of monitoring data are presented in Appendix D.