Agreement No. CE 20/2004(EP) North East
New Territories (NENT) Landfill Extension Monthly Environmental Monitoring and Audit
Report (No. 23) – October 2024 |
Contents
12 Environmental Non-conformance
13 Implementation Status on Environmental Mitigation
Measures
Figure
Location of the Project Site |
|
Impact Air Quality, Noise & Surface Water Monitoring Locations |
|
Landfill
Gas Monitoring Locations |
Appendix
Construction Programme & Construction Site Activities |
|
Project Organization Chart & Management Structure |
|
Detail Status of FEP & EP Submission |
|
Monitoring Schedule for Reporting Month & Next Month |
|
Calibration Certificates |
|
Monitoring Results |
|
Graphical Presentations |
|
Notification of Environmental Quality Limits Exceedance |
|
Wind Data |
|
Waste Flow Table |
|
Joint Environmental Site Inspection Records |
|
Environmental Mitigation Implementation Schedule (EMIS) |
|
Mitigation Measures of Cultural Landscape Features |
|
Cumulative Complaint / Enquiry Log, Summaries of Complaints and Enquiries |
ES1.
Aurecon Hong Kong Limited
(Aurecon) was appointed to undertake the role of Environmental Team (ET) and
carry out Environmental Monitoring and Audit for the North East New Territories
(NENT) Landfill Extension.
ES2.
The construction phase and EM&A
programme of the Project commenced on 1 December 2022.
ES3.
This 23rd Monthly EM&A
Report presents the EM&A works conducted from 1 to 31 October 2024 in
accordance with the Updated EM&A Manual.
Summary
of Construction Works undertaken during Report Period
ES4. The major construction works undertaken during the reporting period include:
ES Table1
Major Construction Works undertaken during
the Reporting Period
-
Construction
of site buildings at Portion D |
-
Site
clearance at Portion A, B2/E1, E3-1 & E4 |
-
Installation of permanent fencing at Portion A,
B1 & E4 |
-
Site
formation at Portion A, B2/E1, E3-1 & E4 |
-
Tree
felling at whole site |
-
Shotcreting (Permanent and Temporary) at whole site |
-
Soil nail installation at Portion A, B2/E1 &
E4 |
Environmental Monitoring and
Audit Progress
ES5. A summary of the monitoring activities in this reporting period is listed below:
ES Table2
Summary of the Monitoring Activities
during the Reporting Period
Times |
Date |
|
-
Air Quality
Monitoring during normal weekdays at each monitoring station |
6 times |
4, 9, 14, 19, 25 & 31 October 2024 |
-
Construction Noise Monitoring during normal
weekdays at each monitoring station |
4 times |
9, 14, 25 & 31 October 2024 |
-
Surface Water Quality Monitoring during normal
weekdays at each monitoring station |
1 time |
9 October 2024 |
-
Landfill Gas Monitoring during normal weekdays for Construction Works |
25 times |
2 to 5, 7 to 10, 12, 14 to 19, 21 to 26, 28 to 31
October 2024 |
4 times |
7, 14, 21 & 28 October 2024 |
Environmental
Exceedance
Air Quality, Noise, Surface Water Quality
Monitoring & Landfill Gas Monitoring
ES6.
No exceedance of the Action and Limit
Levels were recorded at designated monitoring stations during the reporting
period.
Environmental
Non-Conformance/Complaint/Summons and Prosecution
ES7.
No non-compliance event, complaint and
summons/prosecutions were recorded during the reporting period.
Reporting Change
ES8. There was no reporting change in the reporting period.
Future
Key Issues
ES9. Works to be undertaken in the next month include:
ES Table3
Major Construction Works undertaken during
the Next Reporting Period
-
Material loading and unloading, backfilling
of material and site traffic at Portion A, SBA to alternative disposal ground |
-
Construction
of site buildings at Portion D |
-
Site
clearance at Portion A, B2/E1, E3-1 & E4 |
-
Installation of permanent fencing at Portion A,
B1 & E4 |
-
Site
formation at Portion A, B2/E1, E3-1 & E4 |
-
Tree
felling at whole site |
-
Shotcreting (Permanent and Temporary) at whole site |
-
Soil nail installation at Portion A, B2/E1 &
E4 |
ES10.
Potential environmental impacts
arising from the above construction activities are mainly associated with air
quality, construction noise, water quality, waste management, landfill gas
monitoring, landscape and visual, cultural heritage and ecology.
1.1 Background
1.1.1 The North East New Territories Landfill Extension (the NENTX Project) is located adjacent to the existing North East New Territories (NENT) Landfill at Ta Kwu Ling. The extension site is located in a valley covering mainly the existing NENT Landfill Stockpile and Borrow Area that was formed to the east of the existing landfill as part of the original site development of the landfill, and layout plan shown in Figure 1.
1.1.2 The NENTX is a designated project. The Environmental Impact Assessment (EIA) Report (AEIAR-111/2007) and an Environmental Monitoring and Audit Manual were approved on 20 September 2007. The project is governed by an Environmental Permit (EP) (EP-292/2007) which was granted on 26 November 2007. A further of EP (FEP) was applied and the FEP (FEP-01/292/2007) was subsequently granted on 28 April 2022. Another further of EP (FEP-02/292/2007) was subsequently granted on 23 August 2023. The Updated EM&A Manual was approved by Director of Environmental Protection (DEP) on 4 January 2024.
1.1.3 In accordance with the requirements specified in Section 2.7 to 2.11 and Section 12.3 of the Updated EM&A Manual and Condition 3.3 of EP and FEP, Monthly EM&A report should be submitted to DEP, within 2 weeks after the end of the reporting month. The submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC).
1.1.4 The construction phase and EM&A programme of the Project commenced on 1 December 2022.
1.2 Nature, Scale and Scope of the captioned Designated Project
1.2.1 The Nature, Scale and Scope of the captioned Designated Project is presented in Table 1-1.
Table 1-1 Nature, Scale and Scope
of the captioned Designated Project
Item(s) |
Content |
Nature
of Designated Project |
Construction and operation of a landfill for waste
as defined in the “Waste Disposal Ordinance” (Cap. 354) |
Scale and Scope of Designated Project |
The Project mainly consists of the followings: - Construction and operation of a landfill extension
of about 70 hectares with a target void space of at least 19 million cubic
metres on the eastern side of the existing NENT Landfill, including the
followings: - i. Site formation and preparation; ii.
Installation of liner system; iii.
Installation of leachate collection, treatment and
disposal facilities; iv.
Installation of gas collection, utilization and
management facilities; v.
Utilities provisions and drainage diversion; vi.
Landfilling operation; vii.
Restoration and aftercare in subsequent stages;
and viii.
Measures to mitigate environmental impacts as well
as environmental monitoring and auditing to be implemented. |
1.3 Purpose of this Report
1.3.1 This is the 23rd Monthly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from 01 to 31 October 2024.
1.4 Structure of the Report
1.4.1 The structure of the report is as follows:
-
details the background, purpose and structure of the report.
Section 2 – Project Information
-
summarises background and scope of the Project, site description, project
organization and contact details, construction programme, the construction
works undertaken and the status of Environmental Permit(s)/License(s) during
the reporting period.
Section 3 – Air Quality Monitoring
Section 5 – Water Quality Monitoring
Section 6 – Waste Management
Section 7 – Landfill Gas Monitoring
Section 8 – Landscape and Visual
Section 10 – Ecological Monitoring
Section 11 – Site Inspection and Audit
Section 12 – Environmental Non-Conformance
Section 13 – Implementation Status on Environmental Mitigation Measures
Section 14 – Future Key Issues
Section 15 – Conclusion
2.1 Construction Activities
2.1.1 Construction programme and a summary of the major construction activities undertaken in this reporting period is shown in Appendix A. The major construction works undertaken during the reporting period is presented in Table 2-1.
Table
2-1 Major Construction Works
undertaken during the Reporting Period
-
Material
loading and unloading, backfilling of material and site traffic at Portion A,
SBA to alternative disposal ground |
-
Construction
of site buildings at Portion D |
-
Site
clearance at Portion A, B2/E1, E3-1 & E4 |
-
Installation of permanent fencing at Portion A,
B1 & E4 |
-
Site
formation at Portion A, B2/E1, E3-1 & E4 |
-
Tree
felling at whole site |
-
Shotcreting (Permanent and Temporary) at whole site |
-
Soil nail installation at Portion A, B2/E1 &
E4 |
2.2 Project Organization & Management Structure
2.2.1 The Project Organization Chart & Management Structure are shown in Appendix B. The key personnel contact information is summarized in Table 2-2.
Table 2-2 Contact Information of Key Personnel
Party |
Name |
Contact Number |
Contractor
(Veolia
Hong Kong Holding Ltd.) |
Mr. Matt Choy |
2902 5296 |
Independent Environmental Checker (IEC) (Meinhardt Infrastructure and Environment Ltd.) |
Ms. Claudine Lee |
2859 5409 |
Environmental Team Leader (ETL) (Aurecon Hong Kong Limited) |
Mr. Fredrick Leong |
3664 6888 |
2.3 Status of Submission required under the EP & FEP during reporting period
2.3.1 The status of statutory environmental compliance with the EP & FEP conditions under the EIAO, submission status under the EP & FEP during reporting period are presented in Table 2-3. The detail status of statutory environmental compliance with the EP & FEP conditions under the EIAO, submission status under the EP & FEP for NENTX project are shown in Appendix C.
Table 2-3 Status of Submissions required under the EP & FEP during Reporting Period
FEP
Condition |
Submission / Measures |
Status |
|
2.3 |
2.1 |
Management Organization of Main
Construction Companies |
Submitted |
2.4 |
2.2 |
Setting up of Community Liaison Group
(CLG) |
Community Liaison Group
was set up. |
2.5 |
2.3 |
Submission of EM&A Manual |
Submitted |
2.6 |
2.4 |
Submission of Preservation of Cultural
Landscape Features |
Submitted |
2.7 |
2.5 |
Submission of Vegetation Survey
(Transplantation Proposal) |
Submitted |
2.8 |
2.6 |
Submission of Translocation Proposal |
Submitted |
2.9 |
2.7 |
Submission of Transplantation Report
and Post-Transplantation Monitoring |
Submitted |
2.10 |
2.8 |
Submission of Translocation Report and Post-Translocation
Monitoring |
Submitted |
2.11 |
2.9 |
Submission of Detailed Landfill Gas
Hazard Assessment Report |
Submitted |
2.12 |
2.10 |
Submission of Waste Management Plan |
Submitted |
3.2 |
3.2 |
Submission of Baseline Monitoring
Report |
Submitted |
3.3 |
3.3 |
Submission of Monthly EM&A Report |
Submitted |
2.4 Status of Environmental Approval Document
2.4.1 A summary of the relevant valid permits, licences, and/or notifications on environmental protection for this Project since the granting of the EP & FEP is presented in Table 2-4.
Permit / Licenses / Notification |
Reference |
Expiry Date |
Remark |
Environmental
Permit (EP) |
EP-292/2007 |
Throughout
the Contract |
Permit
granted on 26 November 2007 |
Further Environmental Permit (FEP) |
FEP-01/292/2007 |
Throughout
the Contract |
Permit
granted on 28 April
2022 |
FEP-02/292/2007 |
Throughout
the Contract |
Permit
granted on 23 August 2023 |
|
Notification
of Construction Works as required under Air Pollution Control (Construction
Dust) Regulation |
479809 |
Throughout
the Construction Phase |
Notified
on 13 May 2022 |
Registration
of Waste Producer under Waste Disposal Ordinance |
7043692 |
Throughout
the Contract |
Registered
on 13 April 2022 |
Construction Noise Permit |
GW-RN1050-24 |
18 December 2024 |
Permit
granted on 6
September 2024 |
Registration
as Chemical Waste Producer |
5213-642-P1034-18 |
Throughout
the Contract |
Registered
on 11 July 2022 |
Effluent
Discharge License under Water Pollution Control Ordinance |
WT00042301-2022 |
31 October 2027 |
Permit granted on 18 October
2022 Variation of Licence (Permit granted on 7 February
2023) |
2.5 Environmental Monitoring and Audit Progress
2.5.1 A summary of the monitoring activities in this reporting period is presented in Table2-5.
Table 2-5 Summary of the Monitoring Activities in this Reporting Period
Items |
Times |
Date |
-
Air Quality Monitoring during normal weekdays at
each monitoring station |
6 times |
4, 9, 14, 19, 25 &
31 October 2024 |
-
Construction Noise Monitoring during normal
weekdays at each monitoring station |
4 times |
9, 14, 25 & 31 October
2024 |
-
Surface Water Quality Monitoring during normal
weekdays at each monitoring station |
1 time |
9 October 2024 |
-
Landfill Gas Monitoring during
normal weekdays for Construction Works |
25 times |
2 to 5, 7 to 10, 12, 14 to
19, 21 to 26, 28 to 31 October 2024 |
-
Joint Environmental Site Inspection |
4 times |
7, 14, 21 & 28 October 2024 |
Air Quality
2.5.2
6 sets of 1-hr & 24-hr TSP construction dust measurement were
carried out at each monitoring stations during normal weekdays of the reporting
period. No Action / Limit Level exceedance for 1-hr & 24-hr TSP impact
monitoring was recorded during the period.
Noise
2.5.3
4 sets of 30-minute construction noise measurement were carried out at
each monitoring stations during normal weekdays of the reporting period. No
exceedance of Action and Limit Levels of construction noise was recorded during
the reporting period.
Groundwater
2.5.4
Site clearance of future landfilling area is in progress. The
installation of groundwater monitoring boreholes will be installed after the
site formation work of the landfilling area. The target commencement period of
groundwater monitoring will be in 2026. No groundwater monitoring is required
before the completion of site formation work of the landfilling area.
Surface Water Quality
2.5.5
1 set of surface water quality measurement were carried out at each
monitoring stations during normal weekdays of the reporting period. No
exceedance of Action and Limit Levels of surface water quality at each
monitoring stations was recorded during the reporting period.
Landfill Gas
2.5.6
25 sets of landfill gas measurement were carried out at the designated
monitoring locations during normal weekdays of the reporting period. No
exceedance of Action and Limit Levels of landfill gas was recorded during the
reporting period.
Landscape and Visual
2.5.7
All the specified and affected LCAs, LRs and VSRs have been monitored
during the reporting period. No exceedance of Action and Limit Levels of
landscape and visual was recorded during the reporting period.
Cultural Heritage
2.5.8
Implementation of the mitigation measures during construction phase of
the Project has been monitored through the regular site inspection/audit.
Ecology
2.5.9
Implementation of the mitigation measures during construction phase of
the Project has been monitored through the regular site inspection/audit.
Environmental Site Inspection
2.5.10
4 weekly environmental site inspections were carried out during the
reporting period. A joint environmental site inspection was carried out by the
representatives of the Employer's Representative (ER), the Contractor, IEC and
the ET on 21 October 2024. The Contractor has generally implemented part of the
mitigation measures as recommended. No general site inspections were conducted
by Environmental Protection Department-Regional Office (North) (EPD-RNG) during
the reporting period.
3.1 Construction Dust
3.1.1.1
In accordance with the Updated EM&A Manual, 1-hr & 24-hr Total Suspended Particulates (TSP)
levels should be measured at the designated air quality monitoring stations in
every 6 days to ensure that any deteriorating air quality could be readily detected,
and timely action shall be undertaken to rectify such situation. For 1-hr TSP
monitoring, the sampling frequency of at least three times in every six-days
should be undertaken when the highest dust impact occurs. The specific time to
start and stop the 24- hr TSP monitoring shall be clearly defined for each
location.
3.1.2 Monitoring Parameters, Frequency and Location
3.1.2.1
According to the Updated EM&A
Manual, three monitoring stations namely AM(D)1, AM(D)2 and AM(D)3 are selected
for the impact monitoring.
3.1.2.2 A baseline monitoring plan has been submitted to IEC and EPD on 31 May 2022 including the proposal with justification of change of monitoring locations. Due to limited access to the original monitoring locations at AM(D)1, AM(D)2 and AM(D)3, the adjusted stations at AM1, AM2 and AM3 were agreed with IEC prior to the baseline and impact monitoring. The locations of adjusted dust monitoring locations are shown in Figure 2.
3.1.2.3 The detailed monitoring schedule is shown in Appendix D. The locations of dust monitoring stations are shown in Table 3-1. The monitoring parameters, frequency and duration are shown in Table 3-2.
Table 3-1 Locations of Dust Monitoring Stations
Monitoring Station |
Representative For |
Monitoring Parameters |
|
AM1 |
Tung Lo Hang |
1-hr and
24-hr TSP |
|
AM2 |
Heung Yuen Wai |
1-hr and 24-hr TSP |
|
AM3 |
Wo Keng Shan Tsuen |
1-hr and
24-hr TSP |
Remarks:
The contractor passed
correspondence including original monitoring locations specified on the Approved
EM&A Manual to the village representatives on 26 April 2022. After a
meeting with Ta Kwu Ling District Rural Committee (RC) Chairman, representative
from the RC and a few villagers on 1 May 2022, all the Village Heads of Wo Keng
Shan Tsuen, Heung Yuen Wai and Lin Ma Hang verbally refused to accept our
proposal for installation of dust and / or noise monitoring equipment within or
next to their villages, for the baseline & impact monitoring.
AM(D)1
Tung Lo Hang, AM(D)2 Heung Yuen Wai, AM(D)3 Wo Keng Shan Tsuen are the air
monitoring stations for the construction phase EM&A programme as identified
in the approved EM&A Manual for the Project. The access to Tung Lo Hang,
Heung Yuen Wai and Wo Keng Shan Tsuen were denied. A search for alternative air monitoring
locations (AM1, AM2 & AM3) was carried out during the site visit.
The
Baseline Monitoring Plan has been submitted to IEC and EPD including the
proposal of change of monitoring locations on 31 May 2022. This arrangement
was conducted between baseline and impact monitoring and has been agreed by the
Independent Environmental Checker (IEC) and no comment received from EPD.
Due
to the adjustment of the location of AM(D)1, AM(D)2 & AM(D)3to AM1, AM2
& AM3, the measured air quality levels at AM1, AM2 & AM3 would
represent the air quality levels at AM(D)1, AM(D)2 & AM(D)3.
Table 3-2 Dust
Impact Monitoring Parameters, Frequency and Duration
Monitoring
Station |
Parameter |
Frequency and Duration |
AM1, AM2, AM3 |
1-hr TSP |
At least 3 times per 6 days |
24-hr TSP |
1 time per 6 days |
3.1.3.1 High volume samplers (HVSs) were used for carrying out 24-hr TSP monitoring. For 1-hr TSP monitoring, direct reading dust meters were used to measure 1-hr TSP levels.
3.1.3.2 Table 3-3 summarises the equipment that were used in the dust monitoring programme. The calibration certificates are shown in Appendix E.
Table 3-3 Dust Monitoring Equipment
Equipment |
Model |