North East New Territories (NENT)
Landfill Extension Baseline Monitoring Report for
Construction Phase – Dust, Noise and Surface Water Monitoring |
Aurecon Hong Kong Limited
Contents
Figure
Location of the Project Site |
|
Baseline Monitoring Locations |
Appendix
Baseline Monitoring Schedule |
|
Calibration Certificates for Baseline Dust, Noise and Surface Water Monitoring |
|
Baseline Monitoring Results for Dust, Noise and Surface Water Monitoring |
|
Graphical Presentation of baseline monitoring |
|
Photo Records of the monitoring locations |
|
Meteorological Data |
Aurecon Hong Kong Limited (Aurecon) was appointed to undertake the role of Environmental Team (ET) and carry out Environmental Monitoring and Audit for the North East New Territories (NENT) Landfill Extension.
An Environmental Permit (EP) No. EP-292/2007 was issued by the Environmental Protection Department (EPD) on 26 November 2007 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-111/2007) approved by the EPD. The latest EP No. FEP-01/292/2007 was subsequently issued by the EPD in April 2022.
In accordance with the requirements specified in Section 2.5, Section 2.10 and Section 12.2 of the approved Environmental Monitoring and Audit (EM&A) and Environmental Permit (EP and FEP) condition 3.2, baseline monitoring report should be submitted to the Director of Environmental Protection (DEP) for approval before commencement of construction.
The baseline monitoring covered Air Quality, Noise and Surface Water Quality. This Baseline Monitoring Report presents the monitoring works between 10 June 2022 and 18 July 2022, and between 29 October 2022 and 11 November 2022. It aims to establish the baseline levels in accordance with the EM&A Manual.
Data collected from baseline air quality, noise and water quality monitoring were reviewed and analyzed to determine the action and limit levels of air quality, noise and water quality impact monitoring during the construction stage of the project. Details of the methodology, locations and results are presented in the report.
1.1. Background
1.1.1. The Environmental Protection Department (EPD) commissioned a study in Year 2000 on the Extension of Existing Landfills and Identification of Potential New Waste Disposal Sites. Amongst the potential sites recommended in this territory-wide study is the extension of the existing North-East New Territories (NENT) Landfill, with a target capacity of about 19 Mm3. The proposed extension of about 70 ha, is located immediately east of the existing NENT Landfill. A large proportion of the Extension area is in fact the Stockpile and Borrow Area of the existing landfill.
1.1.2. The North-East New Territories Landfill Extension (the NENTX Project) is a designated project. The Environmental Impact Assessment (EIA) Report (AEIAR-111/2007) and an Environmental Monitoring and Audit Manual were approved on 20 September 2007. The project is governed by an Environmental Permit (EP) (EP-292/2007) which was granted on 26 November 2007. A further of EP (FEP) was applied and the FEP (FEP-01/292/2007) was subsequently granted in April 2022.
1.1.3. In accordance with the requirements specified in Section 2.5, Section 2.10 and Section 12.2 of the approved Environmental Monitoring and Audit (EM&A) and Environmental Permit (EP and FEP) condition 3.2, baseline monitoring report should be submitted to the Director of Environmental Protection (DEP) for approval before commencement of construction.
1.1.4. Aurecon Hong Kong Limited (Aurecon) was appointed to undertake the role of Environmental Team (ET) for the baseline monitoring programme. The baseline monitoring covered Air Quality, Noise and Surface Water Quality.
1.2. Purpose of this Report
1.2.1. The purpose of this report is to set the baseline levels for air quality, noise and surface water. These baseline levels will be used as the basis for compliance check during the impact monitoring in construction stage of the Project. It also collects information and observations on the site characteristics prior to the commencement of construction in order to make comparisons between pre-development and post-development.
1.2.2. This baseline monitoring report presents the findings of the baseline monitoring programme conducted between 10 June 2022 and 18 July 2022, and between 29 October 2022 and 11 November 2022. It presents the monitoring locations, equipment, period, methodology, results and observations for Air Quality, Noise and Surface Water Quality during the baseline period.
1.3.1. The structure of the report is as follows:
Section 4 – Surface Water Monitoring
2.1.1
According to the EM&A Manual, baseline dust monitoring was conducted
for 14 consecutive days prior commissioning of the construction. 1-hr TSP
baseline monitoring was conducted between 26 June 2022 and 13 July 2022 at AM1
and AM3, and between 4 July 2022 and 17 July 2022 at AM2, inclusive of both
days. 24-hr TSP baseline monitoring was conducted between 26 June 2022 and 13
July 2022 at AM1 and AM3, and between 4 July 2022 and 18 July 2022 at AM2, inclusive
of both days.
2.2 Monitoring Parameters, Frequency and Location
2.2.1
According to the EM&A
Manual, three monitoring stations namely AM(D)1, AM(D)2 and AM(D)3 are selected
for the baseline monitoring.
2.2.2
A baseline
monitoring plan has been submitted to IEC and EPD including the proposal of
change of monitoring locations. Due to limited access to the original
monitoring locations at AM(D)1, AM(D)2 and AM(D)3, the
adjusted stations at AM1, AM2 and AM3 were agreed with IEC prior to the
baseline monitoring. The locations of
adjusted dust monitoring locations are shown in Figure 2.
2.2.3
Adverse weather was recorded between 30 June 2022 and 3 July 2022 and
typhoon signal no. 8 was hoisted from 1 July 2022 to 2 July 2022. The dust
monitoring was suspended between 30 June 2022 and 3 July 2022 at AM1 and AM3
due to safety concern. As such, additional monitoring dates were conducted from
10 July 2022 to 13 July 2022 for AM1 and AM3.
2.2.4
Due to electricity and technical issues, the High Volume Sampler would
need to be checked before operation. 24-hr TSP monitoring at AM2 on 15 July
2022 was suspended and it was resumed on 16 July 2022.
2.2.5
The detailed monitoring schedule is shown in Appendix A. The frequency and duration are shown in Table 2-2.
Table 2-1 Locations of Dust Monitoring Stations
Monitoring Station |
Representative for |
Monitoring Parameters |
AM1 |
Tung Lo Hang |
1-hr and 24-hrTSP |
AM2 |
Heung Yuen Wai |
1-hr and 24-hrTSP |
AM3 |
Wo Keng Shan Tsuen |
1-hr and 24-hrTSP |
Table 2-2 Dust
Baseline Monitoring Parameters, Frequency and Duration
Monitoring Station |
Parameter |
Frequency and Duration |
AM1, AM2, AM3 |
1-hr TSP |
At least 3 times per day for 14 consecutive days |
24-hr TSP |
Daily sample for
14 consecutive days |
2.3.1
High volume samplers (HVSs) were used for carrying out 24-hr TSP monitoring. For 1-hr TSP monitoring, direct reading dust
meters were used to measure 1-hr TSP levels.
2.3.2
Table 2-3 summarises the equipment that were used in the baseline dust monitoring
programme. The calibration certificates
are shown in Appendix B.
Table 2-3 Dust Monitoring Equipment
Equipment |
Model |
Monitoring Station |
High
Volume Sampler (HVS) |
TE-5170X (S/N: 1856) |
AM1 |
TE-5170X (S/N:
2894) |
AM2 |
|
TE-5170X (S/N: 1855) |
AM3 |
|
Direct Reading Dust Meter |
Sibata LD-5R
(S/N: 0Z4544) |
AM1 |
Sibata LD-5R (S/N: 0Z4545) |
AM2 |
|
Sibata LD-5R
(S/N: 882150) |
AM3 |
|
Calibration Kit (for HVS) |
Tisch TE-5028A (S/N: 3702) |
AM1 |
Tisch TE-5025A
(S/N: 1612) |
AM2 |
|
Tisch TE-5028A (S/N: 3702) |
AM3 |
2.4.1
The 1-hr TSP impact monitoring was conducted using a portable direct
reading dust meter.
2.4.2
The measuring procedures of the
1-hr dust meter has been undertaken in accordance with the Manufacturer’s
Instruction Manual as follows:
2.4.3
The 24-hr TSP baseline monitoring has been conducted using a High Volume
Sampler (HVS).
2.4.4
The HVS has been set-up at the monitoring
location with a fixed power supply for operation. The measuring procedures of
the 24-hr TSP measurements has been undertaken in accordance with the
specifications listed in the EM&A Manual.
Each HVS includes a motor, a filter holder, a flow controller and a
sampling inlet in accordance with the performance specification of the USEPA
Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50), Appendix
B. The measuring procedures of the 24-hr dust meter was
undertaken in accordance with the Manufacturer’s Instruction Manual as follows:
2.4.5
In addition, site conditions and dust sources were recorded in a standard
form for direct input into a database.
2.5.1 The baseline dust monitoring results are summarized in Table 2-4 and the monitoring data together with graphical presentations are presented in Appendix C and Appendix D.
Dust Monitoring Station |
Average 1-hr TSP Concentration, µg/m³ (Range) |
Average 24-hr TSP Concentration, µg/m³ (Range) |
AM1 |
54 (32 – 84) |
53 (24 – 109) |
AM2 |
45 (23 – 61) |
33 (13 – 57) |
AM3 |
54 (37 – 74) |
51 (27 – 81) |
2.6.1
During the baseline monitoring period. wind data from existing weather
station in the vicinity of the designated monitoring location, i.e. Ta Kwu Ling
station operated by Hong Kong Observatory was adopted. It is considered that the
wind data obtained from Ta Kwu Ling station are representative of the Project
area and could be used for the baseline dust monitoring programme for the
Project. The results for wind data monitoring are presented in Appendix F.
2.6.1
2.7 Action and Limit Level for Air Quality (Dust)
2.7.1
The action and limit levels for construction dust are defined in Table 2-5.
Parameters |
Action Level |
Limit (ug/m3) |
24-hr TSP |
For baseline level ≤ 200 mg/m3, Action level = (130% of
baseline level + Limit level)/2 For baseline level > 200 mg/m3, Action level = Limit level |
260 |
1-hr TSP |
For baseline level ≤ 384 mg/m3, Action level = (130% of baseline level
+ Limit level)/2 For baseline level > 384 mg/m3, Action level = Limit level |
500 |
2.7.2 Following the above criteria, the Action and Limit Levels for air quality impact monitoring is presented in Table 2-6 and Table 2-7.
Location |
Action Level, µg/m³ |
Limit Level, µg/m³ |
AM1 |
285 |
500 |
AM2 |
279 |
500 |
AM3 |
285 |
500 |
Location |
Action Level, µg/m³ |
Limit Level, µg/m³ |
AM1 |
164 |
260 |
AM2 |
152 |
260 |
AM3 |
163 |
260 |
2.8.1 The action and limit levels for air quality monitoring are defined in Table 2-6 and 2-7. Should non-compliance of the criteria occurs, action in accordance with the action plan in Table 2-8 shall be carried out.
Event |
ET |
IEC |
Contractor |
Exceedance of Action Level |
|||
1.Exceedance for one sample |
• Identify source • Prepare
Notification of Exceedance • Inform IEC and
Contractor • Repeat
measurement to confirm findings •
Increase monitoring frequency to
daily if exceedance is due to the Project and continue until the monitoring
results reduce to below action level |
• Verify the
Notification of Exceedance • Check monitoring
data submitted by ET and Contractor's working methods • Discuss with ET
and Contractor on proposed remedial measures |
•
Rectify any unacceptable practice •
Amend working methods if appropriate |
2.Exceedance for two or more
consecutive samples |
•
Identify source •
Prepare Notification of Exceedance •
Inform Contractor and IEC •
Repeat measurements to confirm findings •
Increase
monitoring frequency to daily if exceedance is due to the Project and
continue until the monitoring results reduce to below action level •
Discuss with IEC for remedial action required •
Ensure remedial measures are properly implemented •
Continue monitoring at daily intervals if exceedance is due to
the Project •
If no exceedance for 3
consecutive days, cease additional monitoring |
•
Verify the Notification of Exceedance •
Check monitoring data submitted by ET and Contractor's working
methods •
Discuss with ET and Contractor on proposed remedial measures •
Review with analysed results submitted by ET •
Review the proposed remedial measures by Contractor •
Supervise the implementation of remedial measures |
• Submit proposals for remedial actions
to IEC within 3 working days of notification • Implement the agreed proposals • Amend proposal if appropriate |
Table 2-8 Event and Action
Plan for dust monitoring
Event |
ET |
IEC |
Contractor |
Exceedance of Limit Level |
|||
1.Exceedance for
one sample |
•
Identify source •
Prepare Notification of Exceedance •
Inform IEC and Contractor •
Repeat measurement to confirm findings •
Increase monitoring frequency to daily if
exceedance is due to the Project and continue until the monitoring results
reduce to below limit level •
Assess effectiveness of
Contractor's remedial actions and keep EPD and IEC informed of the results |
•
Verify the Notification of Exceedance •
Check monitoring data submitted by ET and
Contractor's working methods •
Discuss with ET and Contractor potential
remedial actions •
Supervise the implementation of remedial
measures |
•
Take immediate action to avoid further
exceedance •
Submit proposals for remedial actions to IEC
within 3 working days of notification •
Implement the agreed proposals •
Amend proposal if appropriate |
2.Exceedance for two or more consecutive samples |
•
Identify source •
Prepare Notification of Exceedance •
Inform IEC and EPD the causes and actions taken for the
exceedances •
Discuss with IEC for remedial action required •
Ensure remedial measures are properly implemented • Assess effectiveness of Contractor’s
remedial actions and keep IEC, EPD and informed of the results • Increase monitoring frequency to
confirm findings •
If exceedance stops, cease additional monitoring |
•
Verify the Notification of Exceedance •
Check monitoring data submitted by ET and Contractor's working
methods •
Discuss amongst ET and Contractor on the potential remedial
actions. •
Review Contractor's remedial actions whenever necessary to
assure their effectiveness •
Supervise the implementation of remedial measures |
• Take immediate action to avoid further
exceedance • Submit proposals for remedial actions
to IEC of notification • Implement the agreed proposals • Resubmit proposals if problem still
not under control •
Stop the relevant activity of works until the exceedance is
abated |
3.1.1
In
accordance with the EM&A manual, noise baseline monitoring shall be carried
out at 2 monitoring stations NM1 and NM2 daily for a period of at least 14
consecutive days. The minimum logging interval shall be 30 minutes with average
of 6 consecutive Leq 5 mins. L10 and L90
shall also
be measured at 5 mins intervals.
3.2 Monitoring Locations, Parameters and Frequency
3.2.1
According
to the EM&A Manual, two monitoring stations namely NM1 and NM2 are selected
for the baseline monitoring.
3.2.2
A baseline
monitoring plan has been submitted to IEC and EPD including the proposal of
change of monitoring locations. Due to limited access to the original monitoring
locations at NM1 and NM2, the adjusted stations at NM1a and NM2a were agreed
with IEC prior to the baseline monitoring. The noise monitoring locations are
summarized in Table 3-1 and shown in Figure 2.
3.2.3
Noise
baseline monitoring was conducted between 27 June 2022 and 17 July 2022 at NM1a
and between 24 June 2022 and 17 July 2022 at NM2a. Due to adverse weather forecast, baseline noise monitoring was suspended
from 1 July 2022 to 3 July 2022 at NM1a and NM2a. The detailed monitoring schedule is shown in Appendix A. The
frequency and duration are shown in Table 3-2.
Monitoring Station |
Representative for |
Type of Measurement |
NM1a |
Wo Keng Shan Tsuen |
Free field |
NM2a |
Lin
Ma Hang |
Free
field |
*For Free
Field measurement, +3dB(A) should be added to the measured results.
Monitoring Station
|
Parameter
|
Frequency and Duration
|
NM1a and NM2a |
LAeq
(30mins) average of
6 consecutive Leq (5min); L10 (5min) & L90 (5min) |
Daily for 14 consecutive days |
3.3.1
Integrating
Sound Level Meters (SLMs) was used for noise baseline monitoring. The SLM
complied with International Electrotechnical Commission Publications 651:1979
(Type 1) and 804:1985 (Type 1) specifications shall be used for carrying out
noise monitoring. The accuracy of the SLM was checked using an acoustic
calibrator generating a known sound pressure level at a known frequency. Measurements shall be accepted as valid only
if the calibration level from prior to and after the noise measurement agrees
to within 1.0dB.
3.3.2
A portable
wind speed meter was used for measuring wind speeds in m/s.
3.3.3
Table 3-3
summarises the equipment that have been used in the baseline noise monitoring
programme. The calibration certificates
are shown in Appendix
A.
Table 3-3 Noise Monitoring Equipment
Equipment |
Model |
Sound Level Meter |
Rion NL-52 (S/N: 01010876, 01010877) |
Acoustic Calibrator |
Rion NC-75 (S/N: 34524163) |
Anemometer |
RS-90 (S/N: 210722168) |
3.4.1
The
details of noise measurement procedures are described as follows:
•
Free-field
measurements were made at the monitoring locations.
•
For free
field, the Sound Level Meter was set at a height of 1.2 m above the ground. The
battery condition was checked to ensure the proper functioning of the meter.
•
Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:
•
Frequency
weighting: A
•
Time
weighting: Fast
•
Measurement
time: 5 minutes (Leq (30-min) would be determined for daytime noise by
calculating the logarithmic average of six Leq (5min) data.)
•
Prior to
and after each noise measurement, the meter was calibrated using a Calibrator
for 94.0 dB at 1000 Hz. If the difference in the calibration level before and
after measurement was more than 1.0 dB, the measurement would be considered
invalid and repeat of noise measurement would be required after recalibration
or repair of the equipment.
•
Noise
measurement should be paused during periods of high intrusive noise if possible
and observation shall be recorded when intrusive noise is not avoided.
•
At the end
of the monitoring period, the Leq, L10 and L90 shall be recorded. In addition,
site conditions and noise sources should be recorded on a standard record sheet.
•
All noise monitoring will be
conducted with the wind speed not exceeding 5m/s and no gusts exceeding 10m/s.
3.5 Baseline Monitoring Result
3.5.1 The baseline noise monitoring results are summarized in Table 3-4, Table 3-5 and Table 3-6. The monitoring data together with graphical presentations are presented in Appendix C and Appendix D.
Noise Monitoring Station |
Average Leq, 30min, dB(A) (Range) |
Average L10, 5min, dB(A)
(Range) |
Average L90, 5min, dB(A)
(Range) |
NM1a |
55.4 (42.7 – 72.5) |
56.0 (41.6 – 78.0) |
51.7 (38.0 – 77.3) |
NM2a |
54.5 (44.7 – 66.4) |
54.5 (38.8 – 74.7) |
49.0 (36.7 – 67.2) |
Remark: *
A correction of +3 dB(A) was made to the free field measurements
Noise Monitoring Station |
Average Leq 5min, dB(A) (Range) |
Average L10, 5min, dB(A)
(Range) |
Average L90, 5min, dB(A)
(Range) |
NM1a |
54.4 (46.4 – 72.2) |
55.7 (47.5 – 73.2) |
52.5 (39.2 – 67.3) |
NM2a |
53.3 (44.5 – 65.0) |
54.7 (42.8 – 69.7) |
50.4 (40 – 63.7) |
Noise Monitoring Station |
Average Leq 5 min, dB(A) (Range) |
Average L10, 5min, dB(A)
(Range) |
Average L90, 5min, dB(A)
(Range) |
NM1a |
53.6 (43.4 – 75.0) |
55.0 (44.5 – 77.3) |
51.3 (39.2 – 72.0) |
NM2a |
52.4 (41.3 – 68.2) |
53.5 (41.3 – 72.7) |
49.1 (38 – 64.4) |
3.5.2 During the baseline monitoring period, the weather condition varied from sunny, cloudy, windy to rainy. No particular observations are identified near the monitoring stations during the baseline monitoring period. The noise monitoring results will be used as a reference of future impact monitoring period.
3.6 Action and Limit Level for Construction Noise
3.6.1
The criteria
for action and limit levels for construction noise are defined in Table 3-7.
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75dB(A) |
If works
are to be carried out during restricted hours, the conditions stipulated in the
construction noise permit issued by the Noise Control Authority have to be
followed.
3.7 Event and Action Plan
3.7.1 The action and limit levels for noise monitoring is defined in Table 3-7. Should non-compliance of the criteria occurs, action in accordance with the action plan in Table 3-8 shall be carried out.
Table 3-8 Event and
action plan for construction noise monitoring
Event |
ET |
IEC |
Contractor |
Exceedance of Action Level |
• Identify source, investigate the causes
of exceedance • Prepare Notification of Exceedance • Inform IEC and Contractor • Report the results of investigation to
IEC, and Contractor • Discuss with Contractor and IEC for
formulate remedial measures • Ensure remedial measures are properly implemented •
Have additional monitoring if exceedance is due to the Project. If
exceedance stops, cease additional monitoring |
• Verify the Notification of Exceedance • Review the analysed results submitted by
ET •
Discuss with ET,
and Contractor on the potential remedial actions • Review the proposed remedial measures •
Supervise the implementation of remedial measures |
• Submit noise mitigation proposals to IEC • Implement the agreed noise mitigation
proposals |
Exceedance
of Limit
Level |
•
Identify source, investigate the causes of
exceedance •
Prepare Notification of Exceedance •
Inform IEC and Contractor •
Repeat measurements to confirm findings •
Discuss with Contractor and IEC for remedial
measures •
Ensure remedial measures are properly implemented •
Assess effectiveness of Contractor’s remedial
actions and keep IEC and EPD informed of the results •
Have additional monitoring if exceedance is due to
the Project. If exceedance stops, cease additional monitoring |
•
Verify the Notification of Exceedance •
Review the analysed results submitted by ET • Discuss with ET, and Contractor on the
potential remedial actions • Review the proposed
remedial measures • Supervise the implementation of remedial
measures |
• Take immediate action to avoid further
exceedance • Submit proposals for remedial actions to IEC
of notification • Implement the agreed proposals • Resubmit proposals if problem still not
under control • Stop the relevant portion of works as
determined by project proponent until the exceedance is abated. |
4.1.1
In
accordance with the EM&A manual, baseline surface water quality monitoring
was carried out at the designated surface water discharge points at WM1 for 3
days per week for 4 consecutive weeks prior to commencement of construction
works of the Project. For WM2, further
discussion has been made with EPD and EPD has agreed the surface water
monitoring at WM2 shall be conducted for 3 days per week for 2 consecutive
weeks during dry season prior to commencement of construction works.
4.2 Monitoring Locations, Parameters, Frequency and Duration
4.2.1
Baseline
surface water monitoring was carried out between 10 June 2022 and 16 July 2022 at
WM1 and between 29 October and 11 November 2022 at WM2. The monitoring
locations are indicated in Table 4-1 and Figure 2.
4.2.2
The
monitoring parameters, frequency and duration of surface water quality baseline
monitoring are summarized in Table 4-2.
4.2.3
At the
week of 27/6, surface water monitoring was planned to be conducted on 28/6,
30/6 and 1/7. Due to adverse weather, the surface water monitoring on 28/6 was
rescheduled to 29/6. In addition, adverse weather was recorded from 30 June
2022 to 3 July 2022, the surface water monitoring was suspended due to safety
concern. As such, additional monitoring was conducted on 14 July 2022 and 16
July 2022 at WM1. Due to
adverse weather from 2 November to 4 November 2022, the surface water
monitoring was suspended due to safety concern and resumed on 5 November 2022
at WM2. Detailed monitoring schedule is presented in Appendix
A.
Table 4-1 Surface water quality
monitoring locations
Monitoring Station
|
Location
|
Coordinates (HK Grid)
|
|
Easting
|
Northing
|
||
WM1 |
Upstream of Lin Ma Hang River |
836665 |
845020 |
WM2 |
Ping Yuen River |
835592 |
844186 |
Table 4-2 Surface water quality
monitoring Parameters, Frequency and Duration
Parameter
|
Frequency
|
Duration
|
pH, Electrical conductivity, DO, Turbidity, SS, Alkalinity, COD,
BOD5, TOC, Ammonia-nitrogen, TKN, Nitrate, Sulphate, Sulphite, Phosphate,
Chloride, Sodium, Mg, Ca, K, Fe, Ni, Zn, Mn, Cu, Pb, Cd, Coliform Count, Oil
and Grease |
3 days per week |
4 consecutive
weeks at WM1 2 consecutive
weeks at WM2* |
*Remark:
The duration of surface water monitoring at WM2 is conducted in 2 consecutive
weeks during dry season as agreed with the EPD. The monitoring parameters for WM2 are pH, DO, Turbidity and SS.
4.3.1
The
measurements of pH, electrical conductivity (EC), DO, water temperature and air
temperature were undertaken in situ. In situ monitoring instruments in
compliance with the specifications listed under Section 5.5 of the EM&A
Manual were used to undertake the surface water quality monitoring for the
Project. Table 4-3 summarises the equipment used in the baseline surface
water quality monitoring works. Copies of the calibration certificates are
attached in Appendix
B.
Table 4-3 Surface
Water Quality Monitoring Equipment
Equipment |
Model |
Water Quality Meter |
Horiba U-53 (S/N: S2A98W8H, THAUKESL) YSI ProDSS (S/N: 22C106561) |
Water Flow Meter |
FP211 (S/N: 1513001493) |
4.4 Summary of Surface Water Quality Monitoring Procedure
Operational/ Analytical Procedures
4.4.1
Water
samples were collected from within 500 mm of the water surface. Water was collected by a small clean
open-mouthed bucket with the lip pointing upstream. Usually, water was then transferred to the
sample bottles until they were filled to the top with no remaining air space
before the lid was securely screwed on.
For samples that were preserved with acid or alkalis prior to transport
to the laboratory, the samples bottles were filled to the level specified by
the analytical laboratory.
4.4.2
Analysis
shall be carried out in accordance with methods described in ASTM or APHA
-AWWA-WEF Standard.
4.4.3
The
testing of parameters presented in Table 4-4 for all stations was
conducted by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066).
Comprehensive quality assurance and control procedures were in place in order
to ensure quality and consistency in results. The detection limits are provided
in Table 4.4.
Table 4-4 Surface
Water Monitoring Detection Limits and Limit of Reporting
Parameters |
Detection Limit |
Limit
of Reporting |
Method
Reference |
pH |
0.1 |
0.1 |
APHA 4500 H+ B |
Electrical conductivity |
1 mS/cm |
1 mS/cm |
APHA 2510 B |
Alkalinity |
1 mg/L |
1 mg/L |
APHA 2320 B |
COD |
10 mg/L |
5 mg/L |
APHA 5220 C |
BOD5 |
3 mg/L |
2 mg/L |
APHA 5210 B |
TOC |
1 mg/L |
1 mg/L |
APHA 5310 B |
SS |
0.1 mg/L |
0.1 mg/L |
APHA 2540 D |
Ammonia-nitrogen |
0.2 mg/L |
0.01 mg/L |
APHA 4500 NH3 G |
TKN |
0.4 mg/L |
0.1 mg/L |
APHA 4500Norg: D |
Nitrate |
0.5 mg/L |
0.01 mg/L |
APHA 4500 NO3 I |
Sulphate |
5 mg/L |
1 mg/L |
USEPA 375.4 |
Sulphite |
2 mg/L |
2 mg/L |
APHA 4500 SO3 B |
Phosphate |
0.01 mg/L |
0.01 mg/L |
APHA 4500-P B & F |
Chloride |
0.5 mg/L |
0.5 mg/L |
USEPA 325.1 |
Sodium |
50 mg/L |
50 mg/L |
USEPA 6010C |
Mg |
50 mg/L |
50 mg/L |
USEPA 6010C |
Ca |
50 mg/L |
50 mg/L |
USEPA 6010C |
K |
50 mg/L |
50 mg/L |
USEPA 6010C |
Fe |
50 mg/L |
10 mg/L |
USEPA 6010C |
Ni |
1 mg/L |
1 mg/L |
USEPA 6020A |
Zn |
10 mg/L |
10 mg/L |
USEPA 6020A |
Mn |
1 mg/L |
1 mg/L |
USEPA 6020A |
Cu |
1 mg/L |
1 mg/L |
USEPA 6020A |
Pb |
1 mg/L |
1 mg/L |
USEPA 6020A |
Cd |
0.2 mg/L |
0.2 mg/L |
USEPA 6020A |
Coliform Count |
1 cfu/ 100mL |
1 cfu/ 100mL |
DoE section 7.8,
7.9.4.1 & 3 |
Oil and Grease |
5 mg/L |
5 mg/L |
APHA 5520 B |
4.4.4
All in
situ monitoring instruments were checked, calibrated and certified by a
laboratory accredited under HOKLAS or other international accreditation scheme
before use, and subsequently re-calibrated at the intervals according to
manufacturer’s requirement throughout all stages of the surface water quality
monitoring programme. Responses of sensors and electrodes were checked with
certified standard solutions before each use. Calibration for a DO meter was
carried out before measurement according to the instruction manual of the
equipment model. For the on-site calibration of field equipment, the
requirements of the BS 1427:2009, "Guide to on-site test methods for the
analysis of waters" was observed.
4.4.5
Water sampling equipment used
during the course of the monitoring programme was decontaminated by manual
washing and rinsed with clean distilled water after each sampling location.
Sampling Management and Supervision
4.4.6
All
sampling bottles were labelled with the sample ID (including the indication of
sampling station), laboratory number and sampling date. Water samples were
dispatched to the testing laboratory for analysis as soon as possible after the
sampling. All samples were stored in a cool box and kept at less than 4°C but
without frozen. All water samples were handled under chain of custody protocols
and relinquished to the laboratory representatives at locations specified by
the laboratory. The laboratory determination works started within 24 hours
after collection of water samples.
Quality Control Measures for Sample Testing
4.4.7
The samples testing was
performed by ALS Technichem (HK) Pty Ltd. The following quality control
programme was performed by the laboratory for every batch of 20 samples:
·
One method blank; and
·
One sample duplicate.
4.5 Baseline Monitoring Results
4.5.1
Baseline surface water quality monitoring was
conducted at WM1 between 10 June 2022 and 16 July 2022 Adverse weather was
observed from 30 June 2022 to 3 July 2022 and typhoon signal no. 8 was hoisted
on 1 July 2022. Surface water quality monitoring was suspended from 30 June to
3 July and resumed on 4 July 2022 at WM1.
4.5.2
Baseline surface water quality monitoring was
conducted between 29 October 2022 and 11 November 2022 at WM2 inclusive of both
days. Due to typhoon signal no. 8 as hoisted on 2 November 2022 and adverse
weather from 3 November to 4 November 2022, surface water monitoring was
suspended from 2 November to 4 November and resumed on 5 November 2022 at WM2.
4.5.3
The detailed monitoring schedule is shown in Appendix A. The
monitoring results at each monitoring station and graphical presentations of
surface water quality (DO, SS and Turbidity) at the monitoring stations are
given in Appendix C and Appendix D.
4.6 Action and Limit Level for Surface Water Monitoring
4.6.1
The criteria
of action and limit levels for surface water monitoring are defined in Table
4-5.
Table 4-5 Criteria
for Action and Limit Levels for Surface Water Quality
Parameter |
Action |
Limit |
DO in mg L-1 |
5 percentile of baseline data |
4 mg L-1 or 1%-ile of baseline data |
pH |
95
percentile of baseline data |
99
percentile of baseline |
Turbidity in NTU |
95 percentile of baseline data |
99 percentile of baseline |
SS
in mg L-1 |
95
percentile of baseline data |
99
percentile of baseline |
Notes
1.
For DO, non-compliance of the water quality limits occurs
when monitoring result is lower than the limits
2.
For turbidity, SS, non-compliance of the water quality limits
occurs when monitoring result is higher than the limits.
3.
For pH, non-compliance of the water quality limits occurs
when monitoring result is outside the specified range
4.6.2 Based on the criteria listed in Table 4-5, the action and limit levels for surface water quality are determined in Table 4-6 and Table 4-7.
Table 4-6 Action and
Limit levels for Surface Water Quality for WM1
Parameter |
Action |
Limit |
DO in mg L-1 |
7.4 |
4.0 |
pH |
7.7 |
7.8 |
Turbidity in NTU |
9.2 |
9.5 |
SS
in mg L-1 |
9.7 |
11.4 |
Table 4-7 Action and
Limit levels for Surface Water Quality for WM2
Parameter |
Action |
Limit |
DO in mg L-1 |
5.0 |
4.0 |
pH |
7.6 |
7.7 |
Turbidity in NTU |
108.3 |
108.9 |
SS
in mg L-1 |
94.5 |
94.7 |
4.7 Event and Action Plan
4.7.1 The action and limit levels for surface water monitoring were defined in Table 4-6 and Table 4-7. Should non-compliance of the criteria occurs, action in accordance with the action plan in Table 4-8 shall be carried out.
Table 4-8 Event and
Action Plan for Water Quality
Event |
ET |
IEC |
Contractor |
Action level being exceeded by one sampling day |
•
Repeat in situ measurement to confirm findings •
Identify source(s) of impact •
Prepare Notification of Exceedance •
Inform IEC and Contractor •
Check monitoring data, all plant, equipment and Contractor’s working
methods •
Repeat measurement on next day of exceedance |
•
Verify Notification of Exceedance • Check monitoring data and Contractor’s working methods |
• Rectify unacceptable practice • Amend working methods if appropriate |
Action level being exceeded by two or more
consecutive sampling days |
• Repeat in situ
measurement to confirm findings •
Identify
source(s) of impact • Prepare Notification
of Exceedance •
Inform
IEC and Contractor •
Check monitoring data, all plant, equipment and
Contractor’s working methods •
Discuss
with Contractor and IEC for remedial measures •
Ensure
mitigation measures are implemented •
Increase
the monitoring frequency to daily until no exceedance of Action level •
Repeat measurement on next day of exceedance |
• Verify Notification of Exceedance • Check monitoring data and Contractor's
working method • Discuss with ET and Contractor on possible
remedial actions • Review the proposed mitigation measures • Supervise the implementation of mitigation
measures |
•
Submit
proposal of additional mitigation measures to IEC of notification •
Implement
the agreed mitigation measures •
Amend
proposal if appropriate |
Limit Level being exceeded by one sampling day |
•
Repeat in situ measurement to confirm findings •
Identify
source(s) of impact •
Prepare Notification of Exceedance •
Inform
IEC and Contractor; •
Check
monitoring data, all plant, equipment and Contractor's working methods •
Discuss
mitigation measures with IEC and Contractor •
Ensure
mitigation measure are implemented |
•
Verify
Notification of
Exceedance •
Check
monitoring data submitted By ET and Contractor’s working method •
Discuss
with ET and Contractor on possible remedial actions •
Review
the proposed mitigation measures •
Supervise
the implementation of mitigation measures |
•
Critically
review the working method •
Rectify
unacceptable practice •
Take
immediate corrective actions to avoid further exceedance •
Submit
proposal of mitigation measures to IEC •
Implement
the agreed mitigation measures •
|
|
|
|
|
|
|
|
|
Limit level being exceeded by two or more
consecutive sampling days |
• Repeat in situ
measurement to confirm findings • Identify source(s) of impact • Prepare Notification
of Exceedance • Inform IEC, contractor and EPD • Check monitoring data, all plant, equipment
and Contractor's working methods • Discuss mitigation measures with IEC and
Contractor • Ensure mitigation measure are implemented |
• Verify Notification of Exceedance •
Check
monitoring data submitted by ET and Contractor’s working method •
Discuss
with ET and Contractor on possible remedial actions •
Review
the proposed mitigation measures • Supervise the implementation of mitigation
measures |
• Critically review the working method •
Rectify
unacceptable practice • Take immediate corrective actions to avoid
further exceedance • Submit proposal of mitigation measures to
IEC • Implement the agreed mitigation measures • Resubmit proposals if problem still not
under control • Slow down or to stop relevant activity until
exceedance is abated |
5.1
In accordance with the approved EM&A
Manual, baseline monitoring for 1-hr TSP, 24-hr TSP, noise and surface water has
been conducted prior to commencement of the construction works.
5.2
1-hr TSP baseline monitoring was conducted
between 26 June 2022 and 13 July 2022 at AM1 and AM3, and between 4 July 2022
and 17 July 2022 at AM2, inclusive of both days. 24-hr TSP baseline monitoring
was conducted between 26 June 2022 and 13 July 2022 at AM1 and AM3, and between
4 July 2022 and 18 July 2022 at AM2, inclusive of both days. The action and limit
levels for dust (1-hr and 24-hr TSP) were established.
5.3
Baseline noise monitoring was conducted
between 27 June 2022 and 17 July 2022 at NM1a and between 24 June 2022 and 17
June 2022 at NM2a, inclusive of both days. The action and limit levels for
noise monitoring were established.
5.4
Baseline surface water quality monitoring
was conducted between 10 June 2022 and 16 July 2022 inclusive of both days at
WM1, and 29 October 2022 and 11 November 2022 inclusive of both days at WM2.
The action and limit levels for surface water monitoring were established.
2.1
This report has summarized the baseline
monitoring locations, requirements and equipment that has been adopted for conducting
1-hr TSP, 24-hr TSP, Noise and Surface Water Quality baseline monitoring. The baseline
monitoring results, weather conditions and observations within the baseline
monitoring period have been presented in this report.
2.1
Figure
2.1
2.1
Appendix A
2.1
Appendix B
2.1
Appendix C
2.1
2.1
Appendix D
2.1
2.1
Appendix E
2.1
2.1
Appendix F
2.1
2.1
2.1
2.1
2.1
2.1
2.1
Prepared
by:
2.1
Aurecon
Hong Kong Limited
2.1
Unit
1608, 16/F, Tower B, Manulife Financial Centre,
2.1
223 –
231 Wai Yip Street, Kwun Tong,
2.1
Kowloon
Hong Kong S. A. R.
2.1
T: +852
3664 6888
2.1
F: +852
3664 6999
2.1
E: hongkong@aurecongroup.com
2.1
2.1
5.5